Project Information Sheet

Part A: Basic Project Information

( Must be completed in all cases )
PIP No: 660
1. PROJECT NAME: Project for Sustainable Productivity Improvement and Economic Efficiency
    ឈ្មោះគម្រោងៈ គម្រោងលើកកម្ពស់ផលិតភាពដំណាំកសិកម្មប្រកបដោយនិរន្តរភាព និងប្រសិទ្ធភាពសេដ្ឋកិច្ច
2. PROJECT DATES:
PROJECT START :

1/1/2026

ESTIMATED COMPLETION :

12/31/2028

3. TOTAL PROJECT COST:
$

30000000

4. RESPONSIBLE MINISTRY:

Ministry of Agriculture, Forestry and Fisheries

RESPONSIBLE UNIT:

General Directorate of Agriculture

អង្គភាព​ទទួល​ខុស​ត្រូវ:

អគ្គនាយកដ្ឋានកសិកម្ម

5. PROJECT STATUS

Planned


DETAILED PROJECT INFORMATION


6. TYPE OF PROJECT:

7. SOURCE OF PROJECT FUNDING:

8. THE POLICY AREA OF THE PENTAGON STRATEGY PHASE I THAT THIS PROJECT FALLS UNDER:
9. THE CONTRIBUTION OF THE PROJECT TO ACHIEVE THE ABOVE POLICY:
The project will improve sustainable production and productivity with strong economic viability and increase farmers' income through large scale production in favorable crop zones, which will attract investment and access to markets.
10. Support to Cambodia Industrial Development Policy
Does this Project support to the implementation of the Cambodia Industrial Development Policy?
Investment Promotion (Investment climate and Development of Special Economic Zones (SEZs) and Preparation of Industrial Zones) | ការជំរុញការទាក់ទាញវិនិយោគ (បរិយាកាសវិនិយោគ និងការអភិវឌ្ឍតំបន់សេដ្ឋកិច្ចពិសេសនិងការរៀបចំតំបន់ឧស្សាហកម្ម)
11. SECTOR:

12. PROJECT LOCATION: (Describe the location of the project and its components.)
All Provinces Banteay Meanchey Battambang Kampong Cham Kampong Chhnang
Kampong Speu Kampong Thom Kampot Kandal Kep
Koh Kong Kratie Mondul Kiri Otdar Meanchey Pailin
Phnom Penh Preah Sihanouk Preah Vihear Prey Veng Pursat
Ratanak Kiri Siem Reap Stung Treng Svay Rieng Takeo
Tbong Khmum
13. PROJECT OBJECTIVE: (Describe the major purpose of the project.)
Increase sustainable production and incomes through coordiated large scale crop production and market linkage.
14. PROJECT DESCRIPTION: (Provide a description of the project and all its components.)
The project omponents: 1. Crop zoning​ for Modern Agricutural Cooperatives 2. Insfrastructure support for the establishment of model mixed cropping system 2. Production of registered rice seed and the establishment of high quality seedling nurseries (vegetables, fruit crops, cashew and pepper) 3. Infrastructure for crop production in Modern Agricultural Cooperatives and financing support
15. PROJECT JUSTIFICATION: (Give reasons why this particular project is considered worthwhile.)
The project will contribute to the MAFF strategy in moving toward (1) modernizing and commercializing​​ the agricultural value chain; (2) public and private investments in the agriculture sector; and (3) growing sustainably and increasing resilience to climate change, which will increase agricultural growth with high competitiveness and inclusivity by providing high-quality products.
16. BENEFITS (Who will benefit, directly and indirectly, from the project?)
Modern Agricultural Cooperatives, Policy Makers, Farmers and Private sectors
17. FEASIBILITY STUDY
Is a "Feasibility Study " for the Project requied?
18. SOCIAL & ENVIRONMENTAL IMPACT: (Briefly describe the effects of the project, if any, on the people and the surrounding environment. Will the project assist in alleviating poverty?)
The project will increase crop production and farmers' incomes through growing in specific big area, getting more investors and market development.
19. CLIMATE CHANGE
a. Is any activity or output of the project related to Climate Change?
If Yes, please indicate
b. How is the project relevant to Climate Change?
Please select a Climate Change related sector of the project and fill up the contribution of the climate change related expenditure compared to the total project cost.
Climate Change-Related Sector
Percentage
Climate Change Relevance
20. DISASTER RISK REDUCTION
Is any activity or output of the project related to Disaster Risk Reduction?
If Yes, please indicate
21. GENDER ANALYSIS: (How does the project affect the roles of the men and women in the project area? Will women be actively involved in the implementation of the project?)
In this project, we expect that the number of women will get benefits from this project is about 50 percent.
22. CAPACITY TO IMPLEMENT: (Does the Ministry have the skills and experience required to implement the project?)
General Directorate of Agriculture has its mandate, structure and human resource, especially Department of Agricultural Land Management, Department of Rice Crop, Department of horticulture and subsidiary crop, Department of Industrial Crop and National Agricultural Laboratory having enough capacity to implement it.
23. STATUS OF PROJECT IMPLEMENTATION: (Provide a brief update on the progress of the project to date. Discuss any major problems causing delays in project implementation.)
N/A
24. PROJECT PRIORITY : (Please indicates the priority ranking of the project decided by the ministry/agency.)
1
25. DONOR INVOLVEMENT: (Provide any information on current or potential donor involvement in the project.)
N/A
26. REFERENCE: (Please upload the project documents, MOU, or agreements with funding agencies including MEF.)

Part B: Project Costs and Funding Sources

( In US$’000 )
INVESTMENT COST20242025
Budget
2026
Estimate
2027
Estimate
2028
Estimate
Total in 2026 - 2028Recurrent Cost Est.
BudgetActual
Operational Expenditure
Salaries
Materials + Admin
Other
Capital Expenditure
Construction
Consultancy (i.e. TA)
Equipment + Furniture
Training
Other
TOTAL COST
FUNDING SOURCES20242025
Budget
2026
Estimate
2027
Estimate
2028
Estimate
Total in 2026 - 2028Recurrent Cost Est.
BudgetActual
Project Revenue
Government Funding
Cash Input
Other Resources
Donor Funding
TOTAL COMMITTED FUNDING
FUNDING REQUIRED

​Project Progress

27.
Quarter Expenditure Percentage of Achievement Progress Description User
Quarter 1 0 0
Quarter 2 0 0
Quarter 3 0 0
Quarter 4 0 0
Total 0 0