Project Information Sheet

Part A: Basic Project Information

( Must be completed in all cases )
PIP No: 1726
1. PROJECT NAME: Constructing Residency for Judges and Prosecutors
    ឈ្មោះគម្រោងៈ ការសាងសង់ផ្ទះមុខងារសម្រាប់​ចៅក្រម​និង​ព្រះរាជអាជ្ញា
2. PROJECT DATES:
PROJECT START :

1/1/2026

ESTIMATED COMPLETION :

12/31/2028

3. TOTAL PROJECT COST:
$

9108750

4. RESPONSIBLE MINISTRY:

Ministry of Justice

RESPONSIBLE UNIT:

Ministry of Justice

អង្គភាព​ទទួល​ខុស​ត្រូវ:

ក្រសួងយុត្តិធម៌

5. PROJECT STATUS

Planned


DETAILED PROJECT INFORMATION


6. TYPE OF PROJECT:

7. SOURCE OF PROJECT FUNDING:

8. THE POLICY AREA OF THE PENTAGON STRATEGY PHASE I THAT THIS PROJECT FALLS UNDER:
9. THE CONTRIBUTION OF THE PROJECT TO ACHIEVE THE ABOVE POLICY:
Strengthening of the effectiveness and quality of justice system
10. Support to Cambodia Industrial Development Policy
Does this Project support to the implementation of the Cambodia Industrial Development Policy?
11. SECTOR:

12. PROJECT LOCATION: (Describe the location of the project and its components.)
All Provinces Banteay Meanchey Battambang Kampong Cham Kampong Chhnang
Kampong Speu Kampong Thom Kampot Kandal Kep
Koh Kong Kratie Mondul Kiri Otdar Meanchey Pailin
Phnom Penh Preah Sihanouk Preah Vihear Prey Veng Pursat
Ratanak Kiri Siem Reap Stung Treng Svay Rieng Takeo
Tbong Khmum
13. PROJECT OBJECTIVE: (Describe the major purpose of the project.)
Providing proper accommodation for judges and prosecutors during their mandate in each province, allowing them to work effectively and efficiently, in order to provide better justice services to citizens.
14. PROJECT DESCRIPTION: (Provide a description of the project and all its components.)
To construct residency for judges and prosecutors who are subject to rotational transfers between provinces. The construction of residency is planned for 10 Provincial Courts: (1) Preah Vihear, (2) Kratie, (3) Banteay Meanchey, (4) Pursat, (5) Kampong Thom, (6) Kampong Cham, (7) Tboung Khmum, (8) Svay Rieng, (9) Kep, and (10) Koh Kong.
15. PROJECT JUSTIFICATION: (Give reasons why this particular project is considered worthwhile.)
In accordance with the policy of the 7th mandate Royal Government, promoting and strengthening the effectiveness of the law and justice system
16. BENEFITS (Who will benefit, directly and indirectly, from the project?)
Judges and prosecutors are the direct beneficiaries. Meanwhile, citizens are the indirect benefit from the project's implementation.
17. FEASIBILITY STUDY
Is a "Feasibility Study " for the Project requied?
18. SOCIAL & ENVIRONMENTAL IMPACT: (Briefly describe the effects of the project, if any, on the people and the surrounding environment. Will the project assist in alleviating poverty?)
This project will not have any impact to the environment and society.
19. CLIMATE CHANGE
a. Is any activity or output of the project related to Climate Change?
b. How is the project relevant to Climate Change?
Please select a Climate Change related sector of the project and fill up the contribution of the climate change related expenditure compared to the total project cost.
Climate Change-Related Sector
Percentage
Climate Change Relevance
20. DISASTER RISK REDUCTION
Is any activity or output of the project related to Disaster Risk Reduction?
21. GENDER ANALYSIS: (How does the project affect the roles of the men and women in the project area? Will women be actively involved in the implementation of the project?)
Women are encouraged to participate in this project.
22. CAPACITY TO IMPLEMENT: (Does the Ministry have the skills and experience required to implement the project?)
The ministry of justice is capable of coordinating project implementation
23. STATUS OF PROJECT IMPLEMENTATION: (Provide a brief update on the progress of the project to date. Discuss any major problems causing delays in project implementation.)
The ministry of justice needs funding to ensure the successful implementation of this project.
24. PROJECT PRIORITY : (Please indicates the priority ranking of the project decided by the ministry/agency.)
4
25. DONOR INVOLVEMENT: (Provide any information on current or potential donor involvement in the project.)
26. REFERENCE: (Please upload the project documents, MOU, or agreements with funding agencies including MEF.)

Part B: Project Costs and Funding Sources

( In US$’000 )
INVESTMENT COST202420252026
Budget
2027
Estimate
2028
Estimate
Total in 2026 - 2028Recurrent Cost Est.
BudgetActualBudgetActual
Operational Expenditure
Salaries
Materials + Admin
Other
Capital Expenditure
Construction
Consultancy (i.e. TA)
Equipment + Furniture
Training
Other
TOTAL COST
FUNDING SOURCES202420252026
Budget
2027
Estimate
2028
Estimate
Total in 2026 - 2028Recurrent Cost Est.
BudgetActualBudgetActual
Project Revenue
Government Funding
Cash Input
Other Resources
Donor Funding
TOTAL COMMITTED FUNDING
FUNDING REQUIRED

​Project Progress

27.
Quarter Expenditure Percentage of Achievement Progress Description User
Quarter 1 0 0
Quarter 2 0 0
Quarter 3 0 0
Quarter 4 0 0
Total 0 0