Project Information Sheet

Part A: Basic Project Information

( Must be completed in all cases )
PIP No: 220
1. PROJECT NAME: Establish and develop small rural enterprises in the context of digital technology
    ឈ្មោះគម្រោងៈ បង្កើត និងអភិវឌ្ឍន៍សហគ្រាសខ្នាតតូចនៅជនបទ ក្នុងបរិបទបច្ចេកវិទ្យាឌីជីថល
2. PROJECT DATES:
PROJECT START :

1/9/2026

ESTIMATED COMPLETION :

12/28/2028

3. TOTAL PROJECT COST:
$

1892300

4. RESPONSIBLE MINISTRY:

Ministry of Rural Development

RESPONSIBLE UNIT:

Department of Rural Economic Development

អង្គភាព​ទទួល​ខុស​ត្រូវ:

នាយកដ្ឋានអភិវឌ្ឍន៍សេដ្ឋកិច្ចជនបទ

5. PROJECT STATUS

Planned


DETAILED PROJECT INFORMATION


6. TYPE OF PROJECT:

7. SOURCE OF PROJECT FUNDING:

8. THE POLICY AREA OF THE PENTAGON STRATEGY PHASE I THAT THIS PROJECT FALLS UNDER:
9. THE CONTRIBUTION OF THE PROJECT TO ACHIEVE THE ABOVE POLICY:
To increase rural employment to achieve the Royal Government's policy in 2050
10. Support to Cambodia Industrial Development Policy
Does this Project support to the implementation of the Cambodia Industrial Development Policy?
11. SECTOR:

12. PROJECT LOCATION: (Describe the location of the project and its components.)
All Provinces Banteay Meanchey Battambang Kampong Cham Kampong Chhnang
Kampong Speu Kampong Thom Kampot Kandal Kep
Koh Kong Kratie Mondul Kiri Otdar Meanchey Pailin
Phnom Penh Preah Sihanouk Preah Vihear Prey Veng Pursat
Ratanak Kiri Siem Reap Stung Treng Svay Rieng Takeo
Tbong Khmum
13. PROJECT OBJECTIVE: (Describe the major purpose of the project.)
Increase employment, create new businesses, accelerate the development of small enterprises in rural areas through modern marketing strategy.
14. PROJECT DESCRIPTION: (Provide a description of the project and all its components.)
The project aims to create new businesses, provide initiatives, group formation and training on small business ideas and the relationship between rural credit and business. The project will help improve the livelihoods of rural people with additional income and employment in addition to their farming activities.
15. PROJECT JUSTIFICATION: (Give reasons why this particular project is considered worthwhile.)
The project is in the policy of economic diversification, which helps to stimulate the national economy to respond to Changes in socio-economic factors, crises and natural disasters.
16. BENEFITS (Who will benefit, directly and indirectly, from the project?)
Villagers living in rural areas especially the poor farmer, disability person and the priority are women. The total members are 8000 person
17. FEASIBILITY STUDY
Is a "Feasibility Study " for the Project requied?
18. SOCIAL & ENVIRONMENTAL IMPACT: (Briefly describe the effects of the project, if any, on the people and the surrounding environment. Will the project assist in alleviating poverty?)
NO
19. CLIMATE CHANGE
a. Is any activity or output of the project related to Climate Change?
b. How is the project relevant to Climate Change?
Please select a Climate Change related sector of the project and fill up the contribution of the climate change related expenditure compared to the total project cost.
Climate Change-Related Sector
Percentage
Climate Change Relevance
20. DISASTER RISK REDUCTION
Is any activity or output of the project related to Disaster Risk Reduction?
21. GENDER ANALYSIS: (How does the project affect the roles of the men and women in the project area? Will women be actively involved in the implementation of the project?)
The main purpose of the project are focus on women group, majority of the members are women
22. CAPACITY TO IMPLEMENT: (Does the Ministry have the skills and experience required to implement the project?)
The department has it own officers that has capacity to implement the project
23. STATUS OF PROJECT IMPLEMENTATION: (Provide a brief update on the progress of the project to date. Discuss any major problems causing delays in project implementation.)
No
24. PROJECT PRIORITY : (Please indicates the priority ranking of the project decided by the ministry/agency.)
9
25. DONOR INVOLVEMENT: (Provide any information on current or potential donor involvement in the project.)
No
26. REFERENCE: (Please upload the project documents, MOU, or agreements with funding agencies including MEF.)

Part B: Project Costs and Funding Sources

( In US$’000 )
INVESTMENT COST20242025
Budget
2026
Estimate
2027
Estimate
2028
Estimate
Total in 2026 - 2028Recurrent Cost Est.
BudgetActual
Operational Expenditure
Salaries
Materials + Admin
Other
Capital Expenditure
Construction
Consultancy (i.e. TA)
Equipment + Furniture
Training
Other
TOTAL COST
FUNDING SOURCES20242025
Budget
2026
Estimate
2027
Estimate
2028
Estimate
Total in 2026 - 2028Recurrent Cost Est.
BudgetActual
Project Revenue
Government Funding
Cash Input
Other Resources
Donor Funding
TOTAL COMMITTED FUNDING
FUNDING REQUIRED

​Project Progress

27.
Quarter Expenditure Percentage of Achievement Progress Description User
Quarter 1 0 0
Quarter 2 0 0
Quarter 3 0 0
Quarter 4 0 0
Total 0 0