Project Information Sheet

Part A: Basic Project Information

( Must be completed in all cases )
PIP No: 311
1. PROJECT NAME: Continuing the International Cooperation with Other Countries in the Region and Development Partners.
    ឈ្មោះគម្រោងៈ ការបន្តកិច្ចសហប្រតិបត្តិការអន្តរជាតិប្រទេសក្នុងតំបន់និងដៃគូអភិវឌ្ឍនានា
2. PROJECT DATES:
PROJECT START :

1/1/2026

ESTIMATED COMPLETION :

12/31/2028

3. TOTAL PROJECT COST:
$

1226862

4. RESPONSIBLE MINISTRY:

National Authority for Combating Drugs

RESPONSIBLE UNIT:

អង្គភាព​ទទួល​ខុស​ត្រូវ:

5. PROJECT STATUS

Planned


DETAILED PROJECT INFORMATION


6. TYPE OF PROJECT:

7. SOURCE OF PROJECT FUNDING:

8. THE POLICY AREA OF THE PENTAGON STRATEGY PHASE I THAT THIS PROJECT FALLS UNDER:
9. THE CONTRIBUTION OF THE PROJECT TO ACHIEVE THE ABOVE POLICY:
Strenghten and extend for implementation of the task as provided in the agreement and UN Conventions on drugs and also to improve the international cooperation with other countries in order to find the support for drug control activities.
10. Support to Cambodia Industrial Development Policy
Does this Project support to the implementation of the Cambodia Industrial Development Policy?
11. SECTOR:

12. PROJECT LOCATION: (Describe the location of the project and its components.)
All Provinces Banteay Meanchey Battambang Kampong Cham Kampong Chhnang
Kampong Speu Kampong Thom Kampot Kandal Kep
Koh Kong Kratie Mondul Kiri Otdar Meanchey Pailin
Phnom Penh Preah Sihanouk Preah Vihear Prey Veng Pursat
Ratanak Kiri Siem Reap Stung Treng Svay Rieng Takeo
Tbong Khmum
13. PROJECT OBJECTIVE: (Describe the major purpose of the project.)
The implementation of the agreements and UN Conventions on drugs will be strenghtened and extended and the international cooperation with other countries wil be improve for
14. PROJECT DESCRIPTION: (Provide a description of the project and all its components.)
To assist for implementation of the agreement and UN Conventions on Drugs and find to support from other courntries in the region for drug control activities effectively.
15. PROJECT JUSTIFICATION: (Give reasons why this particular project is considered worthwhile.)
Drug offence is a transnational organized crime so it is necessary to strenghten and extend the international cooperation with other countries in the region.
16. BENEFITS (Who will benefit, directly and indirectly, from the project?)
Government and the people
17. FEASIBILITY STUDY
Is a "Feasibility Study " for the Project requied?
If YES, has it been carried out?
18. SOCIAL & ENVIRONMENTAL IMPACT: (Briefly describe the effects of the project, if any, on the people and the surrounding environment. Will the project assist in alleviating poverty?)
This project does not affect to people and environment surrounding and poverity will be reduced
19. CLIMATE CHANGE
a. Is any activity or output of the project related to Climate Change?
If Yes, please indicate
b. How is the project relevant to Climate Change?
Please select a Climate Change related sector of the project and fill up the contribution of the climate change related expenditure compared to the total project cost.
Climate Change-Related Sector
Percentage
Climate Change Relevance
20. DISASTER RISK REDUCTION
Is any activity or output of the project related to Disaster Risk Reduction?
If Yes, please indicate
21. GENDER ANALYSIS: (How does the project affect the roles of the men and women in the project area? Will women be actively involved in the implementation of the project?)
This project does not affect to men and woment and women will be able to implement this project.
22. CAPACITY TO IMPLEMENT: (Does the Ministry have the skills and experience required to implement the project?)
Members of NACD have skills and experiences for implementation of this project.
23. STATUS OF PROJECT IMPLEMENTATION: (Provide a brief update on the progress of the project to date. Discuss any major problems causing delays in project implementation.)
24. PROJECT PRIORITY : (Please indicates the priority ranking of the project decided by the ministry/agency.)
2
25. DONOR INVOLVEMENT: (Provide any information on current or potential donor involvement in the project.)
26. REFERENCE: (Please upload the project documents, MOU, or agreements with funding agencies including MEF.)

Part B: Project Costs and Funding Sources

( In US$’000 )
INVESTMENT COST20242025
Budget
2026
Estimate
2027
Estimate
2028
Estimate
Total in 2026 - 2028Recurrent Cost Est.
BudgetActual
Operational Expenditure
Salaries
Materials + Admin
Other
Capital Expenditure
Construction
Consultancy (i.e. TA)
Equipment + Furniture
Training
Other
TOTAL COST
FUNDING SOURCES20242025
Budget
2026
Estimate
2027
Estimate
2028
Estimate
Total in 2026 - 2028Recurrent Cost Est.
BudgetActual
Project Revenue
Government Funding
Cash Input
Other Resources
Donor Funding
TOTAL COMMITTED FUNDING
FUNDING REQUIRED

​Project Progress

27.
Quarter Expenditure Percentage of Achievement Progress Description User
Quarter 1 0 0
Quarter 2 0 0
Quarter 3 0 0
Quarter 4 0 0
Total 0 0