1. PROJECT NAME: Conservation and Restoration of Prasat Chen, Koh Ker Heritage Site
    ឈ្មោះគម្រោងៈ គម្រោងអភិរក្សនិងជួសជុលប្រាសាទចិន នៃរមណីយដ្ឋានប្រាសាទកោះកេរ
2. PROJECT DATES:
PROJECT START :

1/1/2025

ESTIMATED COMPLETION :

12/31/2032

3. TOTAL PROJECT COST:
$

1188000

4. RESPONSIBLE MINISTRY:

Ministry of Culture & Fine Arts

RESPONSIBLE UNIT:

National Authority for Preah Vihear

អង្គភាព​ទទួល​ខុស​ត្រូវ:

អាជ្ញាធរជាតិព្រះវិហារ

5. PROJECT STATUS

Planned


DETAILED PROJECT INFORMATION


6. TYPE OF PROJECT:

7. SOURCE OF PROJECT FUNDING:

8. THE POLICY AREA OF THE PENTAGON STRATEGY PHASE I THAT THIS PROJECT FALLS UNDER:
9. THE CONTRIBUTION OF THE PROJECT TO ACHIEVE THE ABOVE POLICY:
Conservation and restoration of Prasat Krachap to gain strength which contribute to promotion of the value of the national cultural heritage
10. Support to Cambodia Industrial Development Policy
Does this Project support to the implementation of the Cambodia Industrial Development Policy?
11. SECTOR:

12. PROJECT LOCATION: (Describe the location of the project and its components.)
All Provinces Banteay Meanchey Battambang Kampong Cham Kampong Chhnang
Kampong Speu Kampong Thom Kampot Kandal Kep
Koh Kong Kratie Mondul Kiri Otdar Meanchey Pailin
Phnom Penh Preah Sihanouk Preah Vihear Prey Veng Pursat
Ratanak Kiri Siem Reap Stung Treng Svay Rieng Takeo
Tbong Khmum
13. PROJECT OBJECTIVE: (Describe the major purpose of the project.)
In order to stabilize temple structure, assure security for tourists and improve heritage value
14. PROJECT DESCRIPTION: (Provide a description of the project and all its components.)
- Document topography, condition of structure and drainage system within ground yard of Prasat Chen - Undertake archaeological excavation to study structure foundation, cultural objects and deposited soil - Prepare restoration site and ground yard for storage of dismantled stone - Remove trees with high risk - Dismantle ancient stone pieces/blocks, test strength of foundation, remove deposited soil, compact and test strength of staircase foundation after compaction - Repair ancient stone pieces/blocks, reassemble and fix cracking area
15. PROJECT JUSTIFICATION: (Give reasons why this particular project is considered worthwhile.)
Prasat Chen consists of different structure which include structure built of brick and sandstone, and structure built of laterite with sandstone. Currently, these temple have been badly damaged, and undertaken intervention through proping and tightened by cable to prevent them from stone fall. Though, many laterite stone is facing to fallen down as a result of strong win, rain and other natural factors, and may cause risk to tourists incidentally if immediate restoration measure is not taken to bring back strength of its structure. In addition, the restoration of the Prasat Chen is to improve value of the ancient temple structure as well as serve for tourism sector.
16. BENEFITS (Who will benefit, directly and indirectly, from the project?)
This project benefits to local community living within the heritage site, school students and university students, national and international researchers and conservationists in the field of archaeology, Royal Government of Cambodia, and national and international tourists who visit the Koh Ker archaeological site.
17. FEASIBILITY STUDY
Is a "Feasibility Study " for the Project requied?
If YES, has it been carried out?
18. SOCIAL & ENVIRONMENTAL IMPACT: (Briefly describe the effects of the project, if any, on the people and the surrounding environment. Will the project assist in alleviating poverty?)
The project has no impact on the people and the environment. The project will help reduce poverty by providing employment to local communities.
19. CLIMATE CHANGE
a. Is any activity or output of the project related to Climate Change?
b. How is the project relevant to Climate Change?
Please select a Climate Change related sector of the project and fill up the contribution of the climate change related expenditure compared to the total project cost.
Climate Change-Related Sector
Percentage
Climate Change Relevance
20. DISASTER RISK REDUCTION
Is any activity or output of the project related to Disaster Risk Reduction?
If Yes, please indicate
21. GENDER ANALYSIS: (How does the project affect the roles of the men and women in the project area? Will women be actively involved in the implementation of the project?)
Man and woman have equal right to implement this project
22. CAPACITY TO IMPLEMENT: (Does the Ministry have the skills and experience required to implement the project?)
Technical staff of the National Authority for Preah Vihear have solid background knowledge and experience for implementing this project
23. STATUS OF PROJECT IMPLEMENTATION: (Provide a brief update on the progress of the project to date. Discuss any major problems causing delays in project implementation.)
24. PROJECT PRIORITY : (Please indicates the priority ranking of the project decided by the ministry/agency.)
11
25. DONOR INVOLVEMENT: (Provide any information on current or potential donor involvement in the project.)
Not yet have
26. REFERENCE: (Please upload the project documents, MOU, or agreements with funding agencies including MEF.)

Part B: Project Costs and Funding Sources

( In US$’000 )
INVESTMENT COST202320242025
Budget
2026
Estimate
2027
Estimate
Total in 2025 - 2027Recurrent Cost Est.
BudgetActualBudgetActual
Operational Expenditure
Salaries
Materials + Admin
Other
Capital Expenditure
Construction
Consultancy (i.e. TA)
Equipment + Furniture
Training
Other
TOTAL COST
FUNDING SOURCES202320242025
Budget
2026
Estimate
2027
Estimate
Total in 2025 - 2027Recurrent Cost Est.
BudgetActualBudgetActual
Project Revenue
Government Funding
Cash Input
Other Resources
Donor Funding
TOTAL COMMITTED FUNDING
FUNDING REQUIRED

​Project Progress

27.
Quarter Expenditure Percentage of Achievement Progress Description User
Quarter 1 0 0
Quarter 2 0 0
Quarter 3 0 0
Quarter 4 0 0
Total 0 0