Project Information Sheet

Part A: Basic Project Information

( Must be completed in all cases )
PIP No: 20
1. PROJECT NAME: Road Asset Management Project and Additional Financing (RAMP-II and RAMP-IIAF, NR4)
    ឈ្មោះគម្រោងៈ គម្រោងគ្រប់គ្រងទ្រព្យសម្បត្តិ​ផ្លូវ​ថ្នល់ ជំហានទី២និងហិរញ្ញប្បទានបន្ថែម (RAMP-II and RAMP-IIAF, NR4)
2. PROJECT DATES:
PROJECT START :

6/1/2016

ESTIMATED COMPLETION :

05/01/2026

3. TOTAL PROJECT COST:
$

177800000

4. RESPONSIBLE MINISTRY:

Ministry of Public Works & Transport

RESPONSIBLE UNIT:

PMU3

អង្គភាព​ទទួល​ខុស​ត្រូវ:

អង្គភាពគ្រប់គ្រងគម្រោងស្ថាបនាផ្លូវថ្នល់៣ ឯ.ឧ​ ផែង សុវិជ្ជានោ

5. PROJECT STATUS

On Going


DETAILED PROJECT INFORMATION


6. TYPE OF PROJECT:

7. SOURCE OF PROJECT FUNDING:

8. THE POLICY AREA OF THE PENTAGON STRATEGY PHASE I THAT THIS PROJECT FALLS UNDER:
9. THE CONTRIBUTION OF THE PROJECT TO ACHIEVE THE ABOVE POLICY:
The project will significantly benefit the rural poor, Including women, living in the project provinces.
10. Support to Cambodia Industrial Development Policy
Does this Project support to the implementation of the Cambodia Industrial Development Policy?
11. SECTOR:

12. PROJECT LOCATION: (Describe the location of the project and its components.)
All Provinces Banteay Meanchey Battambang Kampong Cham Kampong Chhnang
Kampong Speu Kampong Thom Kampot Kandal Kep
Koh Kong Kratie Mondul Kiri Otdar Meanchey Pailin
Phnom Penh Preah Sihanouk Preah Vihear Prey Veng Pursat
Ratanak Kiri Siem Reap Stung Treng Svay Rieng Takeo
Tbong Khmum
13. PROJECT OBJECTIVE: (Describe the major purpose of the project.)
To improve the condition, safety and climate resilience of selected national road corridors in Cambodia.
14. PROJECT DESCRIPTION: (Provide a description of the project and all its components.)
The project will systematically introduce the design that includes climate proofing and road safety measure and the use of performance based contracts.
15. PROJECT JUSTIFICATION: (Give reasons why this particular project is considered worthwhile.)
The project aims to upgrade about 218km of national road in Kampot, Preah Sihanouk, Tbong Khmum and Kratie province from double Bituminous Surface Treatment road paved conditions to Asphalt Concrete paved roads through performance based contracts.
16. BENEFITS (Who will benefit, directly and indirectly, from the project?)
Improvement of the national roads under the project will serve about 1,000,000 project beneficiaries, the vast majority of whom are the rural poor.
17. FEASIBILITY STUDY
Is a "Feasibility Study " for the Project requied?
If YES, has it been carried out?
18. SOCIAL & ENVIRONMENTAL IMPACT: (Briefly describe the effects of the project, if any, on the people and the surrounding environment. Will the project assist in alleviating poverty?)
No adverse social and environmental impact as this project is only to improve the roads that have been rehabilitated in 2004.
19. CLIMATE CHANGE
a. Is any activity or output of the project related to Climate Change?
b. How is the project relevant to Climate Change?
Please select a Climate Change related sector of the project and fill up the contribution of the climate change related expenditure compared to the total project cost.
Climate Change-Related Sector
Percentage
Climate Change Relevance
20. DISASTER RISK REDUCTION
Is any activity or output of the project related to Disaster Risk Reduction?
21. GENDER ANALYSIS: (How does the project affect the roles of the men and women in the project area? Will women be actively involved in the implementation of the project?)
The project is follow the nation contractual policy for us civil work that a minimum inclusion of at least 25% of female worker in the unskilled racket and equal pay for equal work.
22. CAPACITY TO IMPLEMENT: (Does the Ministry have the skills and experience required to implement the project?)
The project will be implement under the implementation arrangement established under Road Asset Management-II (RAM-II).
23. STATUS OF PROJECT IMPLEMENTATION: (Provide a brief update on the progress of the project to date. Discuss any major problems causing delays in project implementation.)
The project is under loan being approved.
24. PROJECT PRIORITY : (Please indicates the priority ranking of the project decided by the ministry/agency.)
19
25. DONOR INVOLVEMENT: (Provide any information on current or potential donor involvement in the project.)
International Development Association (IDA-WB)
26. REFERENCE: (Please upload the project documents, MOU, or agreements with funding agencies including MEF.)

Part B: Project Costs and Funding Sources

( In US$’000 )
INVESTMENT COST202320242025
Budget
2026
Estimate
2027
Estimate
Total in 2025 - 2027Recurrent Cost Est.
BudgetActualBudgetActual
Operational Expenditure
Salaries
Materials + Admin
Other
Capital Expenditure
Construction
Consultancy (i.e. TA)
Equipment + Furniture
Training
Other
TOTAL COST
FUNDING SOURCES202320242025
Budget
2026
Estimate
2027
Estimate
Total in 2025 - 2027Recurrent Cost Est.
BudgetActualBudgetActual
Project Revenue
Government Funding
Cash Input
Other Resources
Donor Funding
World Bank
TOTAL COMMITTED FUNDING
FUNDING REQUIRED

​Project Progress

27.
Quarter Expenditure Percentage of Achievement Progress Description User
Quarter 1 0 0
Quarter 2 0 0
Quarter 3 0 0
Quarter 4 0 0
Total 0 0