Project Information Sheet

Part A: Basic Project Information

( Must be completed in all cases )
PIP No: 1359
1. PROJECT NAME: Rehabilitation of Prek canal project, Chroy Pros commune, Koh Kong district, Koh Kong province, and construction of a fishing port
    ឈ្មោះគម្រោងៈ គម្រោងជីកស្តារព្រែកឃុំជ្រោយប្រស់ ស្រុកកោះកុង ខេត្តកោះកុង និងសាងសង់កំពង់ផែនេសាទ
2. PROJECT DATES:
PROJECT START :

1/1/2025

ESTIMATED COMPLETION :

12/31/2027

3. TOTAL PROJECT COST:
$

7500000

4. RESPONSIBLE MINISTRY:

Ministry of Public Works & Transport

RESPONSIBLE UNIT:

General Department of Inland Waterway Transport and Port

អង្គភាព​ទទួល​ខុស​ត្រូវ:

អគ្គនាយកដ្ឋានដឹកជញ្ជូនផ្លូវទឹក ផ្លូវសមុទ្រ និងកំពងផែ

5. PROJECT STATUS

Planned


DETAILED PROJECT INFORMATION


6. TYPE OF PROJECT:

7. SOURCE OF PROJECT FUNDING:

8. THE POLICY AREA OF THE PENTAGON STRATEGY PHASE I THAT THIS PROJECT FALLS UNDER:
9. THE CONTRIBUTION OF THE PROJECT TO ACHIEVE THE ABOVE POLICY:
Coordinate the management of water, sea and port transportation
10. Support to Cambodia Industrial Development Policy
Does this Project support to the implementation of the Cambodia Industrial Development Policy?
11. SECTOR:

12. PROJECT LOCATION: (Describe the location of the project and its components.)
All Provinces Banteay Meanchey Battambang Kampong Cham Kampong Chhnang
Kampong Speu Kampong Thom Kampot Kandal Kep
Koh Kong Kratie Mondul Kiri Otdar Meanchey Pailin
Phnom Penh Preah Sihanouk Preah Vihear Prey Veng Pursat
Ratanak Kiri Siem Reap Stung Treng Svay Rieng Takeo
Tbong Khmum
13. PROJECT OBJECTIVE: (Describe the major purpose of the project.)
1) Open the navigation route 2) Facilitate important transportation in the province and cross from the province to the border 3) Improve people's living standards 4) Excavation of canals and construction of ports
14. PROJECT DESCRIPTION: (Provide a description of the project and all its components.)
Excavation of 40 m bottom canal, 20 m bottom, 4 m depth with a length of 6,000 m (the first step restored 200,000 m2) and excavation of the fishing boat size 200m x 200m, depth 4m. Construction of a concrete port, steel wire for docking fishing boats, and pouring large stones to protect the legs.
15. PROJECT JUSTIFICATION: (Give reasons why this particular project is considered worthwhile.)
An important part to open navigation for transporting all kinds of goods and transporting local travelers to the border.
16. BENEFITS (Who will benefit, directly and indirectly, from the project?)
To contribute to the economic development of Cambodia, connect water transport and local fishermen in Koh Kong district.
17. FEASIBILITY STUDY
Is a "Feasibility Study " for the Project requied?
If YES, has it been carried out?
18. SOCIAL & ENVIRONMENTAL IMPACT: (Briefly describe the effects of the project, if any, on the people and the surrounding environment. Will the project assist in alleviating poverty?)
Help reduce poverty
19. CLIMATE CHANGE
a. Is any activity or output of the project related to Climate Change?
b. How is the project relevant to Climate Change?
Please select a Climate Change related sector of the project and fill up the contribution of the climate change related expenditure compared to the total project cost.
Climate Change-Related Sector
Percentage
Climate Change Relevance
20. DISASTER RISK REDUCTION
Is any activity or output of the project related to Disaster Risk Reduction?
If Yes, please indicate
21. GENDER ANALYSIS: (How does the project affect the roles of the men and women in the project area? Will women be actively involved in the implementation of the project?)
Don't have
22. CAPACITY TO IMPLEMENT: (Does the Ministry have the skills and experience required to implement the project?)
The Department of Water Infrastructure and Port Construction of the General Department of Inland Waterway Transport and Ports, Ministry of Public Works and Transport, has sufficient capacity and experience to implement the above stone port construction projects.
23. STATUS OF PROJECT IMPLEMENTATION: (Provide a brief update on the progress of the project to date. Discuss any major problems causing delays in project implementation.)
Graduated and prepared an estimate list to pump the rehabilitation Compensation contracts and agreements may cause delays in project implementation
24. PROJECT PRIORITY : (Please indicates the priority ranking of the project decided by the ministry/agency.)
8
25. DONOR INVOLVEMENT: (Provide any information on current or potential donor involvement in the project.)
Don't have
26. REFERENCE: (Please upload the project documents, MOU, or agreements with funding agencies including MEF.)

Part B: Project Costs and Funding Sources

( In US$’000 )
INVESTMENT COST202320242025
Budget
2026
Estimate
2027
Estimate
Total in 2025 - 2027Recurrent Cost Est.
BudgetActualBudgetActual
Operational Expenditure
Salaries
Materials + Admin
Other
Capital Expenditure
Construction
Consultancy (i.e. TA)
Equipment + Furniture
Training
Other
TOTAL COST
FUNDING SOURCES202320242025
Budget
2026
Estimate
2027
Estimate
Total in 2025 - 2027Recurrent Cost Est.
BudgetActualBudgetActual
Project Revenue
Government Funding
Cash Input
Other Resources
Donor Funding
TOTAL COMMITTED FUNDING
FUNDING REQUIRED

​Project Progress

27.
Quarter Expenditure Percentage of Achievement Progress Description User
Quarter 1 0 0
Quarter 2 0 0
Quarter 3 0 0
Quarter 4 0 0
Total 0 0