Project Information Sheet

Part A: Basic Project Information

( Must be completed in all cases )
PIP No: 1334
1. PROJECT NAME: Groundwater Management in the Country Wide
    ឈ្មោះគម្រោងៈ ការគ្រប់គ្រងទឹកក្រោមដី នៅតាមបណ្តាខេត្ត
2. PROJECT DATES:
PROJECT START :

2/3/2025

ESTIMATED COMPLETION :

12/22/2027

3. TOTAL PROJECT COST:
$

5000000

4. RESPONSIBLE MINISTRY:

Ministry of Water Resources & Meteorology

RESPONSIBLE UNIT:

អង្គភាព​ទទួល​ខុស​ត្រូវ:

នាយកដ្ឋានទឹកស្អាត និងអនាម័យ

5. PROJECT STATUS

Planned


DETAILED PROJECT INFORMATION


6. TYPE OF PROJECT:

7. SOURCE OF PROJECT FUNDING:

8. THE POLICY AREA OF THE PENTAGON STRATEGY PHASE I THAT THIS PROJECT FALLS UNDER:
9. THE CONTRIBUTION OF THE PROJECT TO ACHIEVE THE ABOVE POLICY:
Glorify National Policy and Food Security
10. Support to Cambodia Industrial Development Policy
Does this Project support to the implementation of the Cambodia Industrial Development Policy?
11. SECTOR:

12. PROJECT LOCATION: (Describe the location of the project and its components.)
All Provinces Banteay Meanchey Battambang Kampong Cham Kampong Chhnang
Kampong Speu Kampong Thom Kampot Kandal Kep
Koh Kong Kratie Mondul Kiri Otdar Meanchey Pailin
Phnom Penh Preah Sihanouk Preah Vihear Prey Veng Pursat
Ratanak Kiri Siem Reap Stung Treng Svay Rieng Takeo
Tbong Khmum
13. PROJECT OBJECTIVE: (Describe the major purpose of the project.)
-Study of surface and groundwater sources. -Research evaluation and prepare long-term medium-term planning project to develop water sources that serve the production of clean water as well as urban wastewater in rural. -Regularly research and evaluation water quality, water sources of surface and groundwater that have been used.
14. PROJECT DESCRIPTION: (Provide a description of the project and all its components.)
-Drilling and air compressor wells cleaning. -Install PVC protect soil collapse and filter screen. -Construction of site and fence around control wells. -Water quality analysis. -Sand for filter into wells and automation tools for measuring water condition in wells.
15. PROJECT JUSTIFICATION: (Give reasons why this particular project is considered worthwhile.)
-Wells are dilapidated and need maintenance. -Officials understanding of techniques and skill related to groundwater is still lacking. -Groundwater technical data analysis and storage program not yet available. -New wells for monitoring and groundwater researching to need right technical standard. -Many institutional factors related to work and groundwater data.
16. BENEFITS (Who will benefit, directly and indirectly, from the project?)
-Enabling sustainable management of groundwater sources in response to climate change. -Improve groundwater study and management to ensure that groundwater become a potential water sources for sociology-economic development.
17. FEASIBILITY STUDY
Is a "Feasibility Study " for the Project requied?
If YES, has it been carried out?
18. SOCIAL & ENVIRONMENTAL IMPACT: (Briefly describe the effects of the project, if any, on the people and the surrounding environment. Will the project assist in alleviating poverty?)
Does not affect the environment and society.
19. CLIMATE CHANGE
a. Is any activity or output of the project related to Climate Change?
If Yes, please indicate
b. How is the project relevant to Climate Change?
Please select a Climate Change related sector of the project and fill up the contribution of the climate change related expenditure compared to the total project cost.
Climate Change-Related Sector
Percentage
Climate Change Relevance
20. DISASTER RISK REDUCTION
Is any activity or output of the project related to Disaster Risk Reduction?
21. GENDER ANALYSIS: (How does the project affect the roles of the men and women in the project area? Will women be actively involved in the implementation of the project?)
Not affect the roles of men and women. Women can join the project.
22. CAPACITY TO IMPLEMENT: (Does the Ministry have the skills and experience required to implement the project?)
The ministry has expertise and experience in project implementation.
23. STATUS OF PROJECT IMPLEMENTATION: (Provide a brief update on the progress of the project to date. Discuss any major problems causing delays in project implementation.)
24. PROJECT PRIORITY : (Please indicates the priority ranking of the project decided by the ministry/agency.)
1
25. DONOR INVOLVEMENT: (Provide any information on current or potential donor involvement in the project.)
Seeking the assistance
26. REFERENCE: (Please upload the project documents, MOU, or agreements with funding agencies including MEF.)

Part B: Project Costs and Funding Sources

( In US$’000 )
INVESTMENT COST202320242025
Budget
2026
Estimate
2027
Estimate
Total in 2025 - 2027Recurrent Cost Est.
BudgetActualBudgetActual
Operational Expenditure
Salaries
Materials + Admin
Other
Capital Expenditure
Construction
Consultancy (i.e. TA)
Equipment + Furniture
Training
Other
TOTAL COST
FUNDING SOURCES202320242025
Budget
2026
Estimate
2027
Estimate
Total in 2025 - 2027Recurrent Cost Est.
BudgetActualBudgetActual
Project Revenue
Government Funding
Cash Input
Other Resources
Donor Funding
TOTAL COMMITTED FUNDING
FUNDING REQUIRED

​Project Progress

27.
Quarter Expenditure Percentage of Achievement Progress Description User
Quarter 1 0 0
Quarter 2 0 0
Quarter 3 0 0
Quarter 4 0 0
Total 0 0