PIP No: 195
1. PROJECT NAME: Rural Sanitation and Hygiene promoting program
    ឈ្មោះគម្រោងៈ លើកកម្ពស់ការផ្តល់សេវាអនាម័យជនបទ
2. PROJECT DATES:
PROJECT START :

1/1/2025

ESTIMATED COMPLETION :

12/31/2027

3. TOTAL PROJECT COST:
$

6450000

4. RESPONSIBLE MINISTRY:

Ministry of Rural Development

RESPONSIBLE UNIT:

Department of Rural Health Care

អង្គភាព​ទទួល​ខុស​ត្រូវ:

នាយកដ្ឋានថែទាំសុខភាពជនបទ

5. PROJECT STATUS

Deleted


DETAILED PROJECT INFORMATION


6. TYPE OF PROJECT:

7. SOURCE OF PROJECT FUNDING:

8. THE POLICY AREA OF THE PENTAGON STRATEGY PHASE I THAT THIS PROJECT FALLS UNDER:
9. THE CONTRIBUTION OF THE PROJECT TO ACHIEVE THE ABOVE POLICY:
To improve rural sanitation and increase rural sanitation coverage
10. Support to Cambodia Industrial Development Policy
Does this Project support to the implementation of the Cambodia Industrial Development Policy?
11. SECTOR:

12. PROJECT LOCATION: (Describe the location of the project and its components.)
All Provinces Banteay Meanchey Battambang Kampong Cham Kampong Chhnang
Kampong Speu Kampong Thom Kampot Kandal Kep
Koh Kong Kratie Mondul Kiri Otdar Meanchey Pailin
Phnom Penh Preah Sihanouk Preah Vihear Prey Veng Pursat
Ratanak Kiri Siem Reap Stung Treng Svay Rieng Takeo
Tbong Khmum
13. PROJECT OBJECTIVE: (Describe the major purpose of the project.)
To educate and raise awareness to community people on water, sanitation and hygiene.
14. PROJECT DESCRIPTION: (Provide a description of the project and all its components.)
Improve rural health care and promote latrine construction in 25 provinces and expand to challenging environment areas such as remote and flooded communities.
15. PROJECT JUSTIFICATION: (Give reasons why this particular project is considered worthwhile.)
Improve the sanitation and hygiene practice of community people which remarkably contribute to achieve the Rectangular Strategy phase IV of RGC​ especially, to achieve government goal in 2025.
16. BENEFITS (Who will benefit, directly and indirectly, from the project?)
Community people including people in challenging environment.
17. FEASIBILITY STUDY
Is a "Feasibility Study " for the Project requied?
18. SOCIAL & ENVIRONMENTAL IMPACT: (Briefly describe the effects of the project, if any, on the people and the surrounding environment. Will the project assist in alleviating poverty?)
This project does not create on social and environment impacts. The project will actually assist in alleviating poverty. Also, make a better environment in rural communities.
19. CLIMATE CHANGE
a. Is any activity or output of the project related to Climate Change?
If Yes, please indicate
b. How is the project relevant to Climate Change?
Please select a Climate Change related sector of the project and fill up the contribution of the climate change related expenditure compared to the total project cost.
Climate Change-Related Sector
Percentage
Climate Change Relevance
18. Livelihoods (general) | ១៨. ជីវភាពរស់នៅ (ទូទៅ)
25
Low
20. DISASTER RISK REDUCTION
Is any activity or output of the project related to Disaster Risk Reduction?
If Yes, please indicate
21. GENDER ANALYSIS: (How does the project affect the roles of the men and women in the project area? Will women be actively involved in the implementation of the project?)
The project strongly promotes women and children’s roles in making decision and educating either their family or community. Women are highly encouraged to involve in implementing this project. Therefore, they will then actively participate​​ and monitor on rural sanitation promotion.
22. CAPACITY TO IMPLEMENT: (Does the Ministry have the skills and experience required to implement the project?)
MRD has knowledgeable and experienced on rural sanitation promotion through different approaches.
23. STATUS OF PROJECT IMPLEMENTATION: (Provide a brief update on the progress of the project to date. Discuss any major problems causing delays in project implementation.)
24. PROJECT PRIORITY : (Please indicates the priority ranking of the project decided by the ministry/agency.)
3
25. DONOR INVOLVEMENT: (Provide any information on current or potential donor involvement in the project.)
Plan international, UNICEF, WSP, SNV, WHO, ADB, World Vision, World Bank, WaterAid, EWM, WaterSHED.
26. REFERENCE: (Please upload the project documents, MOU, or agreements with funding agencies including MEF.)

Part B: Project Costs and Funding Sources

( In US$’000 )
INVESTMENT COST20242025202620272028Total in 2026 - 2028Recurrent Cost Est.
Operational Expenditure
Salaries
Materials + Admin
Other
Capital Expenditure
Construction
Consultancy (i.e. TA)
Equipment + Furniture
Training
Other
TOTAL COST
FUNDING SOURCES20242025202620272028Total in 2026 - 2028Recurrent Cost Est.
Project Revenue
Government Funding
Cash Input
Other Resources
Donor Funding
TOTAL COMMITTED FUNDING
FUNDING REQUIRED

​Project Progress

27.
Quarter Expenditure Percentage of Achievement Progress Description User
Quarter 1 0 0
Quarter 2 0 0
Quarter 3 0 0
Quarter 4 0 0
Total 0 0