Project Information Sheet

Part A: Basic Project Information

( Must be completed in all cases )
PIP No: 1299
1. PROJECT NAME: Implement Climate Change and Disaster Resilient Construction and Infrastructure Standards
    ឈ្មោះគម្រោងៈ ការអនុវត្តកសាងភាពធន់ទៅនឹងការប្រែប្រួលអាកាសធាតុ និងគ្រោះមហន្តរាយលើ ស្តង់ដាហេដ្ឋារចនាសម្ព័ន្ធ និងសំណង់អគារ
2. PROJECT DATES:
PROJECT START :

1/1/2024

ESTIMATED COMPLETION :

12/31/2025

3. TOTAL PROJECT COST:
$

400000

4. RESPONSIBLE MINISTRY:

National Committee for Disaster Management

RESPONSIBLE UNIT:

General Secretariat of the National Committee for Disaster Management

អង្គភាព​ទទួល​ខុស​ត្រូវ:

អគ្គលេខាធិការដ្ឋានគណៈកម្មាធិការជាតិគ្រប់គ្រងគ្រោះមហន្តរាយ

5. PROJECT STATUS

Planned


DETAILED PROJECT INFORMATION


6. TYPE OF PROJECT:

7. SOURCE OF PROJECT FUNDING:

8. THE POLICY AREA OF THE PENTAGON STRATEGY PHASE I THAT THIS PROJECT FALLS UNDER:
9. THE CONTRIBUTION OF THE PROJECT TO ACHIEVE THE ABOVE POLICY:
Implement climate change and disaster resilient construction and infrastructure standards: - Technical guidelines cross-beneficial to other sectors - Potential for community groups (e.g. school support committees) to be involved in construction/retrofitting - Increased energy-efficiency, and use of climate-aware products
10. Support to Cambodia Industrial Development Policy
Does this Project support to the implementation of the Cambodia Industrial Development Policy?
11. SECTOR:

12. PROJECT LOCATION: (Describe the location of the project and its components.)
All Provinces Banteay Meanchey Battambang Kampong Cham Kampong Chhnang
Kampong Speu Kampong Thom Kampot Kandal Kep
Koh Kong Kratie Mondul Kiri Otdar Meanchey Pailin
Phnom Penh Preah Sihanouk Preah Vihear Prey Veng Pursat
Ratanak Kiri Siem Reap Stung Treng Svay Rieng Takeo
Tbong Khmum
13. PROJECT OBJECTIVE: (Describe the major purpose of the project.)
Implement climate change and disaster resilient construction and infrastructure standards
14. PROJECT DESCRIPTION: (Provide a description of the project and all its components.)
Implement climate change and disaster resilient construction and infrastructure standards: - 100% of new building compliant with climate and disaster resilient construction guidelines - Conditional: 20% of older buildings retrofitted - Established guidelines for incorporating climate and disaster risk assessments into design and construction of new buildings and critical infrastructures (school, health facility and other facilities). - Established or improved national legislative frameworks for resilient construction and its implementation mechanism.
15. PROJECT JUSTIFICATION: (Give reasons why this particular project is considered worthwhile.)
Implement climate change and disaster resilient construction and infrastructure standards: - Increased infrastructure resilience to withstand impacts of disasters - Interlinked with energy-efficiency policies for Climate Change Adaptation.
16. BENEFITS (Who will benefit, directly and indirectly, from the project?)
Implement climate change and disaster resilient construction and infrastructure standards: - Technical guidelines cross-beneficial to other sectors - Potential for community groups (e.g. school support committees) to be involved in construction/retrofitting - Increased energy-efficiency, and use of climate-aware products
17. FEASIBILITY STUDY
Is a "Feasibility Study " for the Project requied?
If YES, has it been carried out?
18. SOCIAL & ENVIRONMENTAL IMPACT: (Briefly describe the effects of the project, if any, on the people and the surrounding environment. Will the project assist in alleviating poverty?)
19. CLIMATE CHANGE
a. Is any activity or output of the project related to Climate Change?
If Yes, please indicate
b. How is the project relevant to Climate Change?
Please select a Climate Change related sector of the project and fill up the contribution of the climate change related expenditure compared to the total project cost.
Climate Change-Related Sector
Percentage
Climate Change Relevance
3. Disaster reduction | ៣. ការកាត់បន្ថយហានិភ័យ
70
Moderate
20. DISASTER RISK REDUCTION
Is any activity or output of the project related to Disaster Risk Reduction?
If Yes, please indicate
21. GENDER ANALYSIS: (How does the project affect the roles of the men and women in the project area? Will women be actively involved in the implementation of the project?)
Women will be actively involved in the implementation of the project due to memberships of women in cross-cutting sectors and from the national to sub-national levels and classification of women as one of vulnerable groups.
22. CAPACITY TO IMPLEMENT: (Does the Ministry have the skills and experience required to implement the project?)
NCDM has enough skills and experience required to implement the project. Most of its technical officials and senior officials have been with NCDM more than 10 years and received short-term. medium and long-term trainings related to disaster risk reduction and management (DRRM) in the country and overseas. Some of the them have been involved in various projects implemented in partnership with donors and civil society. NCDM has the Disaster Management law, legal framework, policies and strategies as well as the disaster management structure from the national to sub-national levels, conductive for effective and successful implementation of the projects.
23. STATUS OF PROJECT IMPLEMENTATION: (Provide a brief update on the progress of the project to date. Discuss any major problems causing delays in project implementation.)
Planning
24. PROJECT PRIORITY : (Please indicates the priority ranking of the project decided by the ministry/agency.)
1
25. DONOR INVOLVEMENT: (Provide any information on current or potential donor involvement in the project.)
26. REFERENCE: (Please upload the project documents, MOU, or agreements with funding agencies including MEF.)

Part B: Project Costs and Funding Sources

( In US$’000 )
INVESTMENT COST202320242025
Budget
2026
Estimate
2027
Estimate
Total in 2025 - 2027Recurrent Cost Est.
BudgetActualBudgetActual
Operational Expenditure
Salaries
Materials + Admin
Other
Capital Expenditure
Construction
Consultancy (i.e. TA)
Equipment + Furniture
Training
Other
TOTAL COST
FUNDING SOURCES202320242025
Budget
2026
Estimate
2027
Estimate
Total in 2025 - 2027Recurrent Cost Est.
BudgetActualBudgetActual
Project Revenue
Government Funding
Cash Input
Other Resources
Donor Funding
TOTAL COMMITTED FUNDING
FUNDING REQUIRED

​Project Progress

27.
Quarter Expenditure Percentage of Achievement Progress Description User
Quarter 1 0 0
Quarter 2 0 0
Quarter 3 0 0
Quarter 4 0 0
Total 0 0