Project Information Sheet

Part A: Basic Project Information

( Must be completed in all cases )
PIP No: 1216
1. PROJECT NAME: Construction 4 headquarters and 30 checkpoints, police, heritage and 9 border protection
    ឈ្មោះគម្រោងៈ សង់ទីបញ្ជាការវរៈ ០4ខ្នង និងប៉ុស្តិ៍ការពារ 30ខ្នង នគរបាលការពារបេតិកភណ្ឌ និងប៉ុស្តិ៍ព្រំដែន9
2. PROJECT DATES:
PROJECT START :

1/3/2024

ESTIMATED COMPLETION :

12/31/2026

3. TOTAL PROJECT COST:
$

1712000

4. RESPONSIBLE MINISTRY:

Ministry of Interior

RESPONSIBLE UNIT:

General Commissariat of National Police

អង្គភាព​ទទួល​ខុស​ត្រូវ:

អគ្គស្នងការដ្ឋាននគរបាលជាតិ

5. PROJECT STATUS

Planned


DETAILED PROJECT INFORMATION


6. TYPE OF PROJECT:

7. SOURCE OF PROJECT FUNDING:

8. THE POLICY AREA OF THE PENTAGON STRATEGY PHASE I THAT THIS PROJECT FALLS UNDER:
9. THE CONTRIBUTION OF THE PROJECT TO ACHIEVE THE ABOVE POLICY:
Contribute to local development for the protection of heritage police officers (Banteay Meanchey - Kampong Thom, Battambang, Preah Vihear, Kampong Cham) and border protection of Kep, Kampot, Preah Sihanouk, Ratanakkiri, Mondulkiri, Stung Treng
10. Support to Cambodia Industrial Development Policy
Does this Project support to the implementation of the Cambodia Industrial Development Policy?
11. SECTOR:

12. PROJECT LOCATION: (Describe the location of the project and its components.)
All Provinces Banteay Meanchey Battambang Kampong Cham Kampong Chhnang
Kampong Speu Kampong Thom Kampot Kandal Kep
Koh Kong Kratie Mondul Kiri Otdar Meanchey Pailin
Phnom Penh Preah Sihanouk Preah Vihear Prey Veng Pursat
Ratanak Kiri Siem Reap Stung Treng Svay Rieng Takeo
Tbong Khmum
13. PROJECT OBJECTIVE: (Describe the major purpose of the project.)
Convenient for heritage protection police officers (Banteay Meanchey-Kampong Thom, Battambang, Preah Vihear, Kampong Cham) and border guards of Kep, Kampot, Sihanoukville, Ratanakkiri, Mondulkiri, Stung Treng
14. PROJECT DESCRIPTION: (Provide a description of the project and all its components.)
- Heritage Police (Banteay Meanchey - Kampong Thom, Battambang, Preah Vihear, Kampong Cham) and Border Protection Kep, Kampot, Preah Sihanouk, Ratanakkiri, Mondulkiri, Stung Treng. -Receive information quickly and easily, issue rescue operations to national and international tourists in a timely manner and stand up to protect the territorial integrity of the people
15. PROJECT JUSTIFICATION: (Give reasons why this particular project is considered worthwhile.)
16. BENEFITS (Who will benefit, directly and indirectly, from the project?)
- Heritage Protection Police (Banteay Meanchey - Kampong Thom, Battambang, Preah Vihear, Kampong Cham) and Border Protection Kep, Kampot, Preah Sihanouk, Ratanakkiri, Mondulkiri, Stung Treng have appropriate command posts - Receive information quickly, launch rescue operations for national and international tourists in a timely manner and stand up to protect the territorial integrity of the people
17. FEASIBILITY STUDY
Is a "Feasibility Study " for the Project requied?
18. SOCIAL & ENVIRONMENTAL IMPACT: (Briefly describe the effects of the project, if any, on the people and the surrounding environment. Will the project assist in alleviating poverty?)
- Heritage Protection Police (Banteay Meanchey - Kampong Thom, Battambang, Preah Vihear, Kampong Cham) and Border Protection Kep, Kampot, Preah Sihanouk, Ratanakkiri, Mondulkiri, Stung Treng have appropriate command posts - Receive information quickly, launch rescue operations for national and international tourists in a timely manner and stand up to protect the territorial integrity of the people, the people have confidence in doing business and have a prosperous life
19. CLIMATE CHANGE
a. Is any activity or output of the project related to Climate Change?
b. How is the project relevant to Climate Change?
Please select a Climate Change related sector of the project and fill up the contribution of the climate change related expenditure compared to the total project cost.
Climate Change-Related Sector
Percentage
Climate Change Relevance
20. DISASTER RISK REDUCTION
Is any activity or output of the project related to Disaster Risk Reduction?
If Yes, please indicate
21. GENDER ANALYSIS: (How does the project affect the roles of the men and women in the project area? Will women be actively involved in the implementation of the project?)
22. CAPACITY TO IMPLEMENT: (Does the Ministry have the skills and experience required to implement the project?)
23. STATUS OF PROJECT IMPLEMENTATION: (Provide a brief update on the progress of the project to date. Discuss any major problems causing delays in project implementation.)
24. PROJECT PRIORITY : (Please indicates the priority ranking of the project decided by the ministry/agency.)
2
25. DONOR INVOLVEMENT: (Provide any information on current or potential donor involvement in the project.)
- Heritage Protection Police (Banteay Meanchey - Kampong Thom, Battambang, Preah Vihear, Kampong Cham) and Border Protection Kep, Kampot, Preah Sihanouk, Ratanakkiri, Mondulkiri, Stung Treng have appropriate command and rescue facilities in time
26. REFERENCE: (Please upload the project documents, MOU, or agreements with funding agencies including MEF.)

Part B: Project Costs and Funding Sources

( In US$’000 )
INVESTMENT COST202320242025
Budget
2026
Estimate
2027
Estimate
Total in 2025 - 2027Recurrent Cost Est.
BudgetActualBudgetActual
Operational Expenditure
Salaries
Materials + Admin
Other
Capital Expenditure
Construction
Consultancy (i.e. TA)
Equipment + Furniture
Training
Other
TOTAL COST
FUNDING SOURCES202320242025
Budget
2026
Estimate
2027
Estimate
Total in 2025 - 2027Recurrent Cost Est.
BudgetActualBudgetActual
Project Revenue
Government Funding
Cash Input
Other Resources
Donor Funding
TOTAL COMMITTED FUNDING
FUNDING REQUIRED

​Project Progress

27.
Quarter Expenditure Percentage of Achievement Progress Description User
Quarter 1 0 0
Quarter 2 0 0
Quarter 3 0 0
Quarter 4 0 0
Total 0 0