1. PROJECT NAME: Climate-Friendly Agribusiness Value Chains Section Project
    ឈ្មោះគម្រោងៈ គម្រោងខែ្សច្រវ៉ាក់ផលិតកម្មដោយភាតរៈបរិស្ថាន
2. PROJECT DATES:
PROJECT START :

12/31/2018

ESTIMATED COMPLETION :

12/31/2024

3. TOTAL PROJECT COST:
$

37350000

4. RESPONSIBLE MINISTRY:

Ministry of Rural Development

RESPONSIBLE UNIT:

Project Implementation Unit

អង្គភាព​ទទួល​ខុស​ត្រូវ:

អង្គភាពអនុវត្តគម្រោង

5. PROJECT STATUS

Deleted


DETAILED PROJECT INFORMATION


6. TYPE OF PROJECT:

7. SOURCE OF PROJECT FUNDING:

8. THE POLICY AREA OF THE PENTAGON STRATEGY PHASE I THAT THIS PROJECT FALLS UNDER:
9. THE CONTRIBUTION OF THE PROJECT TO ACHIEVE THE ABOVE POLICY:
Improve the infrastructure of the agricultural production chain to be better and more weather-resistant
10. Support to Cambodia Industrial Development Policy
Does this Project support to the implementation of the Cambodia Industrial Development Policy?
11. SECTOR:

12. PROJECT LOCATION: (Describe the location of the project and its components.)
All Provinces Banteay Meanchey Battambang Kampong Cham Kampong Chhnang
Kampong Speu Kampong Thom Kampot Kandal Kep
Koh Kong Kratie Mondul Kiri Otdar Meanchey Pailin
Phnom Penh Preah Sihanouk Preah Vihear Prey Veng Pursat
Ratanak Kiri Siem Reap Stung Treng Svay Rieng Takeo
Tbong Khmum
13. PROJECT OBJECTIVE: (Describe the major purpose of the project.)
Improving the travel of people living in the target provinces to facilitate access to markets and farming communities
14. PROJECT DESCRIPTION: (Provide a description of the project and all its components.)
Improve the infrastructure of the agricultural production chain to be better and more weather-resistant
15. PROJECT JUSTIFICATION: (Give reasons why this particular project is considered worthwhile.)
Climate-Friendly Agribusiness Value Chains Section
16. BENEFITS (Who will benefit, directly and indirectly, from the project?)
Improve the infrastructure of the agricultural production chain to be better and more weather-resistant
17. FEASIBILITY STUDY
Is a "Feasibility Study " for the Project requied?
If YES, has it been carried out?
18. SOCIAL & ENVIRONMENTAL IMPACT: (Briefly describe the effects of the project, if any, on the people and the surrounding environment. Will the project assist in alleviating poverty?)
The environmental part of the project is provided according to the proposed project, such as improvement on existing roads, not widening the road.
19. CLIMATE CHANGE
a. Is any activity or output of the project related to Climate Change?
b. How is the project relevant to Climate Change?
Please select a Climate Change related sector of the project and fill up the contribution of the climate change related expenditure compared to the total project cost.
Climate Change-Related Sector
Percentage
Climate Change Relevance
4. Climate change proofing of Infrastructure | ៤. ការសាងសង់ហេដ្ឋារចនាសម្ព័ន្ធដោយបានដាក់បញ្ចូលការប្រែប្រួលអាកាសធាតុ
20
Low
20. DISASTER RISK REDUCTION
Is any activity or output of the project related to Disaster Risk Reduction?
If Yes, please indicate
21. GENDER ANALYSIS: (How does the project affect the roles of the men and women in the project area? Will women be actively involved in the implementation of the project?)
The government, through the Ministry of Rural Development, will ensure that gender analysis is fully implemented and that all project activities are designed and implemented in accordance with gender policies.
22. CAPACITY TO IMPLEMENT: (Does the Ministry have the skills and experience required to implement the project?)
The Ministry of Rural Development has sufficient skills and experience to implement this project.
23. STATUS OF PROJECT IMPLEMENTATION: (Provide a brief update on the progress of the project to date. Discuss any major problems causing delays in project implementation.)
Selected detailed planning consultants and technical inspectors for road construction, combination planning and climate change consultants.
24. PROJECT PRIORITY : (Please indicates the priority ranking of the project decided by the ministry/agency.)
1
25. DONOR INVOLVEMENT: (Provide any information on current or potential donor involvement in the project.)
ADB Bank
26. REFERENCE: (Please upload the project documents, MOU, or agreements with funding agencies including MEF.)

Part B: Project Costs and Funding Sources

( In US$’000 )
INVESTMENT COST20232024202520262027Total in 2025 - 2027Recurrent Cost Est.
Operational Expenditure
Salaries
Materials + Admin
Other
Capital Expenditure
Construction
Consultancy (i.e. TA)
Equipment + Furniture
Training
Other
TOTAL COST
FUNDING SOURCES20232024202520262027Total in 2025 - 2027Recurrent Cost Est.
Project Revenue
Government Funding
Cash Input
Other Resources
Donor Funding
ADB
TOTAL COMMITTED FUNDING
FUNDING REQUIRED

​Project Progress

27.
Quarter Expenditure Percentage of Achievement Progress Description User
Quarter 1 0 0
Quarter 2 0 0
Quarter 3 0 0
Quarter 4 0 0
Total 0 0