Project Information Sheet

Part A: Basic Project Information

( Must be completed in all cases )
PIP No: 1232
1. PROJECT NAME: Construct The Mekong Library and IT Building at Prek Leap National Institute of Agriculture
    ឈ្មោះគម្រោងៈ Construct The Mekong Library and IT Building
2. PROJECT DATES:
PROJECT START :

1/1/2022

ESTIMATED COMPLETION :

12/31/2024

3. TOTAL PROJECT COST:
$

5000000

4. RESPONSIBLE MINISTRY:

Ministry of Agriculture, Forestry and Fisheries

RESPONSIBLE UNIT:

Prek Leap National Institute of Agriculture

អង្គភាព​ទទួល​ខុស​ត្រូវ:

5. PROJECT STATUS

Deleted


DETAILED PROJECT INFORMATION


6. TYPE OF PROJECT:

7. SOURCE OF PROJECT FUNDING:

8. THE POLICY AREA OF THE PENTAGON STRATEGY PHASE I THAT THIS PROJECT FALLS UNDER:
9. THE CONTRIBUTION OF THE PROJECT TO ACHIEVE THE ABOVE POLICY:
Helping improve educational and research quality of students and lecturers at Prek Leap National Institute of Agriculture .
10. Support to Cambodia Industrial Development Policy
Does this Project support to the implementation of the Cambodia Industrial Development Policy?
11. SECTOR:

12. PROJECT LOCATION: (Describe the location of the project and its components.)
All Provinces Banteay Meanchey Battambang Kampong Cham Kampong Chhnang
Kampong Speu Kampong Thom Kampot Kandal Kep
Koh Kong Kratie Mondul Kiri Otdar Meanchey Pailin
Phnom Penh Preah Sihanouk Preah Vihear Prey Veng Pursat
Ratanak Kiri Siem Reap Stung Treng Svay Rieng Takeo
Tbong Khmum
13. PROJECT OBJECTIVE: (Describe the major purpose of the project.)
Modernize Institute Library with advanced IT facility.
14. PROJECT DESCRIPTION: (Provide a description of the project and all its components.)
Build capacity of students and lecturers
15. PROJECT JUSTIFICATION: (Give reasons why this particular project is considered worthwhile.)
The current library is old with no space for reading, not available books and appropriate facilities for students and lecturers to get more information.
16. BENEFITS (Who will benefit, directly and indirectly, from the project?)
students, researchers, lecturers, professors, and others
17. FEASIBILITY STUDY
Is a "Feasibility Study " for the Project requied?
If YES, has it been carried out?
18. SOCIAL & ENVIRONMENTAL IMPACT: (Briefly describe the effects of the project, if any, on the people and the surrounding environment. Will the project assist in alleviating poverty?)
Provided library for research and education.
19. CLIMATE CHANGE
a. Is any activity or output of the project related to Climate Change?
If Yes, please indicate
b. How is the project relevant to Climate Change?
Please select a Climate Change related sector of the project and fill up the contribution of the climate change related expenditure compared to the total project cost.
Climate Change-Related Sector
Percentage
Climate Change Relevance
20. DISASTER RISK REDUCTION
Is any activity or output of the project related to Disaster Risk Reduction?
If Yes, please indicate
21. GENDER ANALYSIS: (How does the project affect the roles of the men and women in the project area? Will women be actively involved in the implementation of the project?)
Both male and female students and lecturers can access the library
22. CAPACITY TO IMPLEMENT: (Does the Ministry have the skills and experience required to implement the project?)
Yes. Institute management having high qualification with Ph.D degree to manage the project.
23. STATUS OF PROJECT IMPLEMENTATION: (Provide a brief update on the progress of the project to date. Discuss any major problems causing delays in project implementation.)
Not yet started.
24. PROJECT PRIORITY : (Please indicates the priority ranking of the project decided by the ministry/agency.)
1
25. DONOR INVOLVEMENT: (Provide any information on current or potential donor involvement in the project.)
Not yet identified.
26. REFERENCE: (Please upload the project documents, MOU, or agreements with funding agencies including MEF.)

Part B: Project Costs and Funding Sources

( In US$’000 )
INVESTMENT COST20232024202520262027Total in 2025 - 2027Recurrent Cost Est.
Operational Expenditure
Salaries
Materials + Admin
Other
Capital Expenditure
Construction
Consultancy (i.e. TA)
Equipment + Furniture
Training
Other
TOTAL COST
FUNDING SOURCES20232024202520262027Total in 2025 - 2027Recurrent Cost Est.
Project Revenue
Government Funding
Cash Input
Other Resources
Donor Funding
TOTAL COMMITTED FUNDING
FUNDING REQUIRED

​Project Progress

27.
Quarter Expenditure Percentage of Achievement Progress Description User
Quarter 1 0 0
Quarter 2 0 0
Quarter 3 0 0
Quarter 4 0 0
Total 0 0