Project Information Sheet

Part A: Basic Project Information

( Must be completed in all cases )
PIP No: 1187
1. PROJECT NAME: Construction of Culture Museum​​ at Kampong Cham Provincial
    ឈ្មោះគម្រោងៈ គម្រោងសាងសង់សារមន្ទីរវប្បធម៌ខេត្តកំពង់ចាម
2. PROJECT DATES:
PROJECT START :

1/1/2025

ESTIMATED COMPLETION :

12/31/2027

3. TOTAL PROJECT COST:
$

450000

4. RESPONSIBLE MINISTRY:

Ministry of Culture & Fine Arts

RESPONSIBLE UNIT:

Ministry of Culture and Fine Arts

អង្គភាព​ទទួល​ខុស​ត្រូវ:

ក្រសួងវប្បធម៌ និងវិចិត្រសិល្បៈ

5. PROJECT STATUS

Planned


DETAILED PROJECT INFORMATION


6. TYPE OF PROJECT:

7. SOURCE OF PROJECT FUNDING:

8. THE POLICY AREA OF THE PENTAGON STRATEGY PHASE I THAT THIS PROJECT FALLS UNDER:
9. THE CONTRIBUTION OF THE PROJECT TO ACHIEVE THE ABOVE POLICY:
Participate in preserving, and raising the value of national heritage, training human resources, reducing and preventing risks to art objects outside the storage to be safely, attracting visitors.
10. Support to Cambodia Industrial Development Policy
Does this Project support to the implementation of the Cambodia Industrial Development Policy?
11. SECTOR:

12. PROJECT LOCATION: (Describe the location of the project and its components.)
All Provinces Banteay Meanchey Battambang Kampong Cham Kampong Chhnang
Kampong Speu Kampong Thom Kampot Kandal Kep
Koh Kong Kratie Mondul Kiri Otdar Meanchey Pailin
Phnom Penh Preah Sihanouk Preah Vihear Prey Veng Pursat
Ratanak Kiri Siem Reap Stung Treng Svay Rieng Takeo
Tbong Khmum
13. PROJECT OBJECTIVE: (Describe the major purpose of the project.)
- The purpose is to keep artefacts outside the storage to be safely, research and filing document for conservation and preservation works, as well as raise the value of cultural heritage throughout the province and contribute to the preservation and conservation of national heritage. Attract national and international tourists to visit the museum. - Exhibits the history and works of ancient Khmer art - transport artifacts scattered in various areas to be stored at the provincial museum. Arrange ancient artefacts in an orderly and easy manner for tourists to visit.
14. PROJECT DESCRIPTION: (Provide a description of the project and all its components.)
- One building consist of ground floor, concrete structure with masonry wall - Size 16m x 30m, 3 entrances - Not include land cost
15. PROJECT JUSTIFICATION: (Give reasons why this particular project is considered worthwhile.)
The purpose of these projects is to save the artefacts in the warehouse. High risk by preserving the national identity, history and ancient works of Khmer art for preservation Across Kampong Cham province.
16. BENEFITS (Who will benefit, directly and indirectly, from the project?)
The Royal Government and the people of Kampong Cham
17. FEASIBILITY STUDY
Is a "Feasibility Study " for the Project requied?
If YES, has it been carried out?
18. SOCIAL & ENVIRONMENTAL IMPACT: (Briefly describe the effects of the project, if any, on the people and the surrounding environment. Will the project assist in alleviating poverty?)
There is no impact on the environment and society. The project can also help people near the area earn extra income.
19. CLIMATE CHANGE
a. Is any activity or output of the project related to Climate Change?
b. How is the project relevant to Climate Change?
Please select a Climate Change related sector of the project and fill up the contribution of the climate change related expenditure compared to the total project cost.
Climate Change-Related Sector
Percentage
Climate Change Relevance
20. DISASTER RISK REDUCTION
Is any activity or output of the project related to Disaster Risk Reduction?
If Yes, please indicate
21. GENDER ANALYSIS: (How does the project affect the roles of the men and women in the project area? Will women be actively involved in the implementation of the project?)
Men and women are the main driving force in contributing to this project is indispensable.
22. CAPACITY TO IMPLEMENT: (Does the Ministry have the skills and experience required to implement the project?)
The Ministry has sufficient skills and experience to implement the project.
23. STATUS OF PROJECT IMPLEMENTATION: (Provide a brief update on the progress of the project to date. Discuss any major problems causing delays in project implementation.)
Not yet start
24. PROJECT PRIORITY : (Please indicates the priority ranking of the project decided by the ministry/agency.)
13
25. DONOR INVOLVEMENT: (Provide any information on current or potential donor involvement in the project.)
No support from development partners
26. REFERENCE: (Please upload the project documents, MOU, or agreements with funding agencies including MEF.)

Part B: Project Costs and Funding Sources

( In US$’000 )
INVESTMENT COST202320242025
Budget
2026
Estimate
2027
Estimate
Total in 2025 - 2027Recurrent Cost Est.
BudgetActualBudgetActual
Operational Expenditure
Salaries
Materials + Admin
Other
Capital Expenditure
Construction
Consultancy (i.e. TA)
Equipment + Furniture
Training
Other
TOTAL COST
FUNDING SOURCES202320242025
Budget
2026
Estimate
2027
Estimate
Total in 2025 - 2027Recurrent Cost Est.
BudgetActualBudgetActual
Project Revenue
Government Funding
Cash Input
Other Resources
Donor Funding
TOTAL COMMITTED FUNDING
FUNDING REQUIRED

​Project Progress

27.
Quarter Expenditure Percentage of Achievement Progress Description User
Quarter 1 0 0
Quarter 2 0 0
Quarter 3 0 0
Quarter 4 0 0
Total 0 0