Project Information Sheet

Part A: Basic Project Information

( Must be completed in all cases )
PIP No: 1182
1. PROJECT NAME: Construction and develop residence of poor community in Ponhea Kraek district of Tbong Khmum province
    ឈ្មោះគម្រោងៈ ការសាងសង់ និងអភិវឌ្ឍន៍លំនៅឋានសហគមន៍ក្រីក្រ នៅស្រុកពញាក្រែក ខេត្តត្បូងឃ្មុំ
2. PROJECT DATES:
PROJECT START :

1/1/2024

ESTIMATED COMPLETION :

12/31/2026

3. TOTAL PROJECT COST:
$

1512000

4. RESPONSIBLE MINISTRY:

Ministry of Social Affairs, Veterans and Youth Rehabilitation

RESPONSIBLE UNIT:

National Social Assistance Fund

អង្គភាព​ទទួល​ខុស​ត្រូវ:

មូលនិធិជាតិជំនួយសង្គម

5. PROJECT STATUS

Deleted


DETAILED PROJECT INFORMATION


6. TYPE OF PROJECT:

7. SOURCE OF PROJECT FUNDING:

8. THE POLICY AREA OF THE PENTAGON STRATEGY PHASE I THAT THIS PROJECT FALLS UNDER:
9. THE CONTRIBUTION OF THE PROJECT TO ACHIEVE THE ABOVE POLICY:
Develop community for poor people in Ponhea Kraek district of Tbong Khmum province offer suitable shelter, health care to other of family. Residence development of poor community will provide opportunity to those families the warmly, who will become the better living in society.
10. Support to Cambodia Industrial Development Policy
Does this Project support to the implementation of the Cambodia Industrial Development Policy?
11. SECTOR:

12. PROJECT LOCATION: (Describe the location of the project and its components.)
All Provinces Banteay Meanchey Battambang Kampong Cham Kampong Chhnang
Kampong Speu Kampong Thom Kampot Kandal Kep
Koh Kong Kratie Mondul Kiri Otdar Meanchey Pailin
Phnom Penh Preah Sihanouk Preah Vihear Prey Veng Pursat
Ratanak Kiri Siem Reap Stung Treng Svay Rieng Takeo
Tbong Khmum
13. PROJECT OBJECTIVE: (Describe the major purpose of the project.)
Improving for living of people is better.
14. PROJECT DESCRIPTION: (Provide a description of the project and all its components.)
-Build houses 210 Houses * 6,500 $ = 1,365,000 $ -Dig well 210 well * 450 $ = 94,500 $ -Build toilets 210 toilets * 250 $ = 52,500$ Total = 1,512,000 $
15. PROJECT JUSTIFICATION: (Give reasons why this particular project is considered worthwhile.)
According to survey in Tbong khmum province.
16. BENEFITS (Who will benefit, directly and indirectly, from the project?)
The poor people in communities 201 families got shelters and the better living.
17. FEASIBILITY STUDY
Is a "Feasibility Study " for the Project requied?
18. SOCIAL & ENVIRONMENTAL IMPACT: (Briefly describe the effects of the project, if any, on the people and the surrounding environment. Will the project assist in alleviating poverty?)
This project does not affect the people and the surrounding environment.
19. CLIMATE CHANGE
a. Is any activity or output of the project related to Climate Change?
b. How is the project relevant to Climate Change?
Please select a Climate Change related sector of the project and fill up the contribution of the climate change related expenditure compared to the total project cost.
Climate Change-Related Sector
Percentage
Climate Change Relevance
20. DISASTER RISK REDUCTION
Is any activity or output of the project related to Disaster Risk Reduction?
21. GENDER ANALYSIS: (How does the project affect the roles of the men and women in the project area? Will women be actively involved in the implementation of the project?)
Women is priority for wife-household.
22. CAPACITY TO IMPLEMENT: (Does the Ministry have the skills and experience required to implement the project?)
The Ministry has both skills and experience required to implement this project.
23. STATUS OF PROJECT IMPLEMENTATION: (Provide a brief update on the progress of the project to date. Discuss any major problems causing delays in project implementation.)
No
24. PROJECT PRIORITY : (Please indicates the priority ranking of the project decided by the ministry/agency.)
6
25. DONOR INVOLVEMENT: (Provide any information on current or potential donor involvement in the project.)
No
26. REFERENCE: (Please upload the project documents, MOU, or agreements with funding agencies including MEF.)

Part B: Project Costs and Funding Sources

( In US$’000 )
INVESTMENT COST20232024202520262027Total in 2025 - 2027Recurrent Cost Est.
Operational Expenditure
Salaries
Materials + Admin
Other
Capital Expenditure
Construction
Consultancy (i.e. TA)
Equipment + Furniture
Training
Other
TOTAL COST
FUNDING SOURCES20232024202520262027Total in 2025 - 2027Recurrent Cost Est.
Project Revenue
Government Funding
Cash Input
Other Resources
Donor Funding
TOTAL COMMITTED FUNDING
FUNDING REQUIRED

​Project Progress

27.
Quarter Expenditure Percentage of Achievement Progress Description User
Quarter 1 0 0
Quarter 2 0 0
Quarter 3 0 0
Quarter 4 0 0
Total 0 0