Project Information Sheet

Part A: Basic Project Information

( Must be completed in all cases )
PIP No: 1124
1. PROJECT NAME: The Project for Improvement of Preah Sihanouk Provincial Referral Hospital
    ឈ្មោះគម្រោងៈ គម្រោងធ្វើ​ឲ្យ​ល្អប្រសើរ​ឡើងមន្ទីរពេទ្យខេត្តព្រះសីហនុ
2. PROJECT DATES:
PROJECT START :

3/17/2025

ESTIMATED COMPLETION :

03/31/2027

3. TOTAL PROJECT COST:
$

66000000

4. RESPONSIBLE MINISTRY:

Ministry of Health

RESPONSIBLE UNIT:

Ministry of Health

អង្គភាព​ទទួល​ខុស​ត្រូវ:

ក្រសួងសុខាភិបាល

5. PROJECT STATUS

On Going


DETAILED PROJECT INFORMATION


6. TYPE OF PROJECT:

7. SOURCE OF PROJECT FUNDING:

8. THE POLICY AREA OF THE PENTAGON STRATEGY PHASE I THAT THIS PROJECT FALLS UNDER:
9. THE CONTRIBUTION OF THE PROJECT TO ACHIEVE THE ABOVE POLICY:
Provided quality of care in general population in Preah Sihanouk province provide targeted and intervention to response public health and health requirement
10. Support to Cambodia Industrial Development Policy
Does this Project support to the implementation of the Cambodia Industrial Development Policy?
11. SECTOR:

12. PROJECT LOCATION: (Describe the location of the project and its components.)
All Provinces Banteay Meanchey Battambang Kampong Cham Kampong Chhnang
Kampong Speu Kampong Thom Kampot Kandal Kep
Koh Kong Kratie Mondul Kiri Otdar Meanchey Pailin
Phnom Penh Preah Sihanouk Preah Vihear Prey Veng Pursat
Ratanak Kiri Siem Reap Stung Treng Svay Rieng Takeo
Tbong Khmum
13. PROJECT OBJECTIVE: (Describe the major purpose of the project.)
To improved health status in all population in Preah Sihanouk province
14. PROJECT DESCRIPTION: (Provide a description of the project and all its components.)
1-To improved regional hospital and other province on health service delivery 2-To strengthening regional hospital
15. PROJECT JUSTIFICATION: (Give reasons why this particular project is considered worthwhile.)
Project is to work together with all relevant partner
16. BENEFITS (Who will benefit, directly and indirectly, from the project?)
All population in Preah Sihanouk province
17. FEASIBILITY STUDY
Is a "Feasibility Study " for the Project requied?
18. SOCIAL & ENVIRONMENTAL IMPACT: (Briefly describe the effects of the project, if any, on the people and the surrounding environment. Will the project assist in alleviating poverty?)
Reduce poverty
19. CLIMATE CHANGE
a. Is any activity or output of the project related to Climate Change?
b. How is the project relevant to Climate Change?
Please select a Climate Change related sector of the project and fill up the contribution of the climate change related expenditure compared to the total project cost.
Climate Change-Related Sector
Percentage
Climate Change Relevance
7. Health (climate sensitive diseases) | ៧. សុខភាព (ជំងឺដែលទាក់ទងនឹងអាកាសធាតុ)
-30
No Relevance
20. DISASTER RISK REDUCTION
Is any activity or output of the project related to Disaster Risk Reduction?
21. GENDER ANALYSIS: (How does the project affect the roles of the men and women in the project area? Will women be actively involved in the implementation of the project?)
50% both sex will be actively involved in the implementation.
22. CAPACITY TO IMPLEMENT: (Does the Ministry have the skills and experience required to implement the project?)
Yes (Provincial Referral Hospital Preah Sihanouk has full capacities)
23. STATUS OF PROJECT IMPLEMENTATION: (Provide a brief update on the progress of the project to date. Discuss any major problems causing delays in project implementation.)
Annual operational budget plan is not sustainable of Provincial Referal Hospital Preah Sihanouk target and cut down some budget activities
24. PROJECT PRIORITY : (Please indicates the priority ranking of the project decided by the ministry/agency.)
1
25. DONOR INVOLVEMENT: (Provide any information on current or potential donor involvement in the project.)
partially support by China
26. REFERENCE: (Please upload the project documents, MOU, or agreements with funding agencies including MEF.)

Part B: Project Costs and Funding Sources

( In US$’000 )
INVESTMENT COST20242025
Budget
2026
Estimate
2027
Estimate
2028
Estimate
Total in 2026 - 2028Recurrent Cost Est.
BudgetActual
Operational Expenditure
Salaries
Materials + Admin
Other
Capital Expenditure
Construction
Consultancy (i.e. TA)
Equipment + Furniture
Training
Other
TOTAL COST
FUNDING SOURCES20242025
Budget
2026
Estimate
2027
Estimate
2028
Estimate
Total in 2026 - 2028Recurrent Cost Est.
BudgetActual
Project Revenue
Government Funding
Cash Input
Other Resources
Donor Funding
TOTAL COMMITTED FUNDING
FUNDING REQUIRED

​Project Progress

27.
Quarter Expenditure Percentage of Achievement Progress Description User
Quarter 1 0 0
Quarter 2 0 0
Quarter 3 0 0
Quarter 4 0 0
Total 0 0