Project Information Sheet

Part A: Basic Project Information

( Must be completed in all cases )
PIP No: 1102
1. PROJECT NAME: Development in Northern Cambodia and Modernization of landing sites and cold-chain in Tonle Sap Lake and Upper Mekong
    ឈ្មោះគម្រោងៈ ការអភិវឌ្ឍន៍ធនធានជលផលនៅភាគខាងជើងនៃប្រទេសកម្ពុជា និងទំនើបភាវូបនីយកម្មផែត្រីនិងច្រវាក់បង្កកនៅទនេ្លសាប ​និងទន្លេមេគង្គលើ
2. PROJECT DATES:
PROJECT START :

1/7/2021

ESTIMATED COMPLETION :

01/07/2025

3. TOTAL PROJECT COST:
$

38000000

4. RESPONSIBLE MINISTRY:

Ministry of Agriculture, Forestry and Fisheries

RESPONSIBLE UNIT:

Fisheries Administration

អង្គភាព​ទទួល​ខុស​ត្រូវ:

រដ្ឋបាលជលផល

5. PROJECT STATUS

Deleted


DETAILED PROJECT INFORMATION


6. TYPE OF PROJECT:

7. SOURCE OF PROJECT FUNDING:

8. THE POLICY AREA OF THE PENTAGON STRATEGY PHASE I THAT THIS PROJECT FALLS UNDER:
9. THE CONTRIBUTION OF THE PROJECT TO ACHIEVE THE ABOVE POLICY:
10. Support to Cambodia Industrial Development Policy
Does this Project support to the implementation of the Cambodia Industrial Development Policy?
11. SECTOR:

12. PROJECT LOCATION: (Describe the location of the project and its components.)
All Provinces Banteay Meanchey Battambang Kampong Cham Kampong Chhnang
Kampong Speu Kampong Thom Kampot Kandal Kep
Koh Kong Kratie Mondul Kiri Otdar Meanchey Pailin
Phnom Penh Preah Sihanouk Preah Vihear Prey Veng Pursat
Ratanak Kiri Siem Reap Stung Treng Svay Rieng Takeo
Tbong Khmum
13. PROJECT OBJECTIVE: (Describe the major purpose of the project.)
To improve fisheries resources management in the selected areas in Stung Treng and Kratie provinces, and develop and modernize landing sites and cold-chain in Tonle Sap region.
14. PROJECT DESCRIPTION: (Provide a description of the project and all its components.)
Subcomponent 1.1: Establishment of Inland Fisheries and Aquaculture Research Institute, USD5,000,000 Subcomponent 1.2: Development of Aquaculture of local high economic value fish species, USD3,000,000 Subcomponent 1.3: Development of Landing Sites and Cold-Chain in Tonle Sap Region, USD30,000,000
15. PROJECT JUSTIFICATION: (Give reasons why this particular project is considered worthwhile.)
Contributing in fisheries resource management, enhancement of fish landing sites and cold-chain fisheries products, and local people livelihoods.
16. BENEFITS (Who will benefit, directly and indirectly, from the project?)
• An estimated 400,000 people will be benefited directly or indirectly in the artisanal fisheries sector in Tonles Sap region and Upper Mekong in Cambodia.
17. FEASIBILITY STUDY
Is a "Feasibility Study " for the Project requied?
If YES, has it been carried out?
18. SOCIAL & ENVIRONMENTAL IMPACT: (Briefly describe the effects of the project, if any, on the people and the surrounding environment. Will the project assist in alleviating poverty?)
The Project will be studied on social and environmental safeguards for proposed building infrastructure in the project sites.
19. CLIMATE CHANGE
a. Is any activity or output of the project related to Climate Change?
b. How is the project relevant to Climate Change?
Please select a Climate Change related sector of the project and fill up the contribution of the climate change related expenditure compared to the total project cost.
Climate Change-Related Sector
Percentage
Climate Change Relevance
20. DISASTER RISK REDUCTION
Is any activity or output of the project related to Disaster Risk Reduction?
21. GENDER ANALYSIS: (How does the project affect the roles of the men and women in the project area? Will women be actively involved in the implementation of the project?)
At least 50% of 100,000 households (or 200,000 people) of community fisheries benefited directly from the projects.
22. CAPACITY TO IMPLEMENT: (Does the Ministry have the skills and experience required to implement the project?)
The Fisheries Administration has capacity to manage.
23. STATUS OF PROJECT IMPLEMENTATION: (Provide a brief update on the progress of the project to date. Discuss any major problems causing delays in project implementation.)
new
24. PROJECT PRIORITY : (Please indicates the priority ranking of the project decided by the ministry/agency.)
1
25. DONOR INVOLVEMENT: (Provide any information on current or potential donor involvement in the project.)
World Bank
26. REFERENCE: (Please upload the project documents, MOU, or agreements with funding agencies including MEF.)

Part B: Project Costs and Funding Sources

( In US$’000 )
INVESTMENT COST20232024202520262027Total in 2025 - 2027Recurrent Cost Est.
Operational Expenditure
Salaries
Materials + Admin
Other
Capital Expenditure
Construction
Consultancy (i.e. TA)
Equipment + Furniture
Training
Other
TOTAL COST
FUNDING SOURCES20232024202520262027Total in 2025 - 2027Recurrent Cost Est.
Project Revenue
Government Funding
Cash Input
Other Resources
Donor Funding
TOTAL COMMITTED FUNDING
FUNDING REQUIRED

​Project Progress

27.
Quarter Expenditure Percentage of Achievement Progress Description User
Quarter 1 0 0
Quarter 2 0 0
Quarter 3 0 0
Quarter 4 0 0
Total 0 0