Project Information Sheet

Part A: Basic Project Information

( Must be completed in all cases )
PIP No: 883
1. PROJECT NAME: Rural Electrification Project Phase 9
    ឈ្មោះគម្រោងៈ គម្រោងពង្រីកបណ្តាញអគ្គិសនីភាវូបនីយកម្មជនបទ ដំណាក់កាលទី៩
2. PROJECT DATES:
PROJECT START :

1/1/2025

ESTIMATED COMPLETION :

12/31/2027

3. TOTAL PROJECT COST:
$

50000000

4. RESPONSIBLE MINISTRY:

Ministry of Mines & Energy

RESPONSIBLE UNIT:

General Department of Energy

អង្គភាព​ទទួល​ខុស​ត្រូវ:

អគ្គនាយកដ្ឋានថាមពល

5. PROJECT STATUS

Planned


DETAILED PROJECT INFORMATION


6. TYPE OF PROJECT:

7. SOURCE OF PROJECT FUNDING:

8. THE POLICY AREA OF THE PENTAGON STRATEGY PHASE I THAT THIS PROJECT FALLS UNDER:
9. THE CONTRIBUTION OF THE PROJECT TO ACHIEVE THE ABOVE POLICY:
The project contributions to reduce the electricity price, as well as increasing the capacity and security of energy supply for long-term economic growth through the expansion of the electricity grid to cover all the villages across the country.
10. Support to Cambodia Industrial Development Policy
Does this Project support to the implementation of the Cambodia Industrial Development Policy?
Four Key Concrete Measures (Energy, Transport, and Transport Policy and Management) | វិធានការគន្លឹះបួនជាក់ស្តែង (ថាមពល ការដឹកជញ្ជូន គោលនយោបាយដឹកជញ្ជូន និងការគ្រប់គ្រងការដឹកជញ្ជូន)
11. SECTOR:

12. PROJECT LOCATION: (Describe the location of the project and its components.)
All Provinces Banteay Meanchey Battambang Kampong Cham Kampong Chhnang
Kampong Speu Kampong Thom Kampot Kandal Kep
Koh Kong Kratie Mondul Kiri Otdar Meanchey Pailin
Phnom Penh Preah Sihanouk Preah Vihear Prey Veng Pursat
Ratanak Kiri Siem Reap Stung Treng Svay Rieng Takeo
Tbong Khmum
13. PROJECT OBJECTIVE: (Describe the major purpose of the project.)
To ensure all villages are electrified in as targeted in the Power Development Plan of the Kingdom.
14. PROJECT DESCRIPTION: (Provide a description of the project and all its components.)
Construction of 2000 km-length-transmission lines
15. PROJECT JUSTIFICATION: (Give reasons why this particular project is considered worthwhile.)
The project has a high priority, and it is listed in the National Energy Development Plan, and it is complied with Rural Electrification Strategy in Cambodia. This project takes into account the National Strategy for Poverty Reduction, and support the Rural Electrification Program in Cambodia.
16. BENEFITS (Who will benefit, directly and indirectly, from the project?)
Almost all residents in Cambodia, especially those are in remote area.
17. FEASIBILITY STUDY
Is a "Feasibility Study " for the Project requied?
If YES, has it been carried out?
18. SOCIAL & ENVIRONMENTAL IMPACT: (Briefly describe the effects of the project, if any, on the people and the surrounding environment. Will the project assist in alleviating poverty?)
There is no major social and environmental impacts
19. CLIMATE CHANGE
a. Is any activity or output of the project related to Climate Change?
If Yes, please indicate
b. How is the project relevant to Climate Change?
Please select a Climate Change related sector of the project and fill up the contribution of the climate change related expenditure compared to the total project cost.
Climate Change-Related Sector
Percentage
Climate Change Relevance
20. DISASTER RISK REDUCTION
Is any activity or output of the project related to Disaster Risk Reduction?
If Yes, please indicate
21. GENDER ANALYSIS: (How does the project affect the roles of the men and women in the project area? Will women be actively involved in the implementation of the project?)
There is no specification
22. CAPACITY TO IMPLEMENT: (Does the Ministry have the skills and experience required to implement the project?)
Yes
23. STATUS OF PROJECT IMPLEMENTATION: (Provide a brief update on the progress of the project to date. Discuss any major problems causing delays in project implementation.)
No information
24. PROJECT PRIORITY : (Please indicates the priority ranking of the project decided by the ministry/agency.)
3
25. DONOR INVOLVEMENT: (Provide any information on current or potential donor involvement in the project.)
china
26. REFERENCE: (Please upload the project documents, MOU, or agreements with funding agencies including MEF.)

Part B: Project Costs and Funding Sources

( In US$’000 )
INVESTMENT COST202320242025
Budget
2026
Estimate
2027
Estimate
Total in 2025 - 2027Recurrent Cost Est.
BudgetActualBudgetActual
Operational Expenditure
Salaries
Materials + Admin
Other
Capital Expenditure
Construction
Consultancy (i.e. TA)
Equipment + Furniture
Training
Other
TOTAL COST
FUNDING SOURCES202320242025
Budget
2026
Estimate
2027
Estimate
Total in 2025 - 2027Recurrent Cost Est.
BudgetActualBudgetActual
Project Revenue
Government Funding
Cash Input
Other Resources
Donor Funding
China
TOTAL COMMITTED FUNDING
FUNDING REQUIRED

​Project Progress

27.
Quarter Expenditure Percentage of Achievement Progress Description User
Quarter 1 0 0
Quarter 2 0 0
Quarter 3 0 0
Quarter 4 0 0
Total 0 0