Project Information Sheet

Part A: Basic Project Information

( Must be completed in all cases )
PIP No: 872
1. PROJECT NAME: Sustainable healthy Tonle Sap Lake management
    ឈ្មោះគម្រោងៈ ការគ្រប់គ្រងសុខមាលភាពបឹងទន្លេសាបប្រកបដោយចិរភាព
2. PROJECT DATES:
PROJECT START :

1/13/2022

ESTIMATED COMPLETION :

12/18/2024

3. TOTAL PROJECT COST:
$

650000

4. RESPONSIBLE MINISTRY:

Ministry of Water Resources & Meteorology

RESPONSIBLE UNIT:

Tonle Sap Authority

អង្គភាព​ទទួល​ខុស​ត្រូវ:

អាជ្ញាធរទន្លេសាប

5. PROJECT STATUS

Deleted


DETAILED PROJECT INFORMATION


6. TYPE OF PROJECT:

7. SOURCE OF PROJECT FUNDING:

8. THE POLICY AREA OF THE PENTAGON STRATEGY PHASE I THAT THIS PROJECT FALLS UNDER:
9. THE CONTRIBUTION OF THE PROJECT TO ACHIEVE THE ABOVE POLICY:
Enhance sustainable water resource and biodivertsity management of Tonle Sap Lake Region and related region.
10. Support to Cambodia Industrial Development Policy
Does this Project support to the implementation of the Cambodia Industrial Development Policy?
11. SECTOR:

12. PROJECT LOCATION: (Describe the location of the project and its components.)
All Provinces Banteay Meanchey Battambang Kampong Cham Kampong Chhnang
Kampong Speu Kampong Thom Kampot Kandal Kep
Koh Kong Kratie Mondul Kiri Otdar Meanchey Pailin
Phnom Penh Preah Sihanouk Preah Vihear Prey Veng Pursat
Ratanak Kiri Siem Reap Stung Treng Svay Rieng Takeo
Tbong Khmum
13. PROJECT OBJECTIVE: (Describe the major purpose of the project.)
- Research - Workshop​ and Training - Publish and disseminate shared understanding
14. PROJECT DESCRIPTION: (Provide a description of the project and all its components.)
1. Formulate the State of Tonle Sap Lake related to the research about socio-enomomic environment and natural resource in the Tonle Sap region 2. determine the issues needs and challenges 3. Consultaion meetings with line ministries and development partners setting the pillar for basin governance 4. Disseminate the guidelines principle and conceptual to access the enhancement Lake basin governance for management, conservation and development Tonle Sap region 5. Capacity building
15. PROJECT JUSTIFICATION: (Give reasons why this particular project is considered worthwhile.)
Ecology system service management framework for integrated water resource management Tonle sap Lake region.
16. BENEFITS (Who will benefit, directly and indirectly, from the project?)
1. Tonle Sap Authority Line ministries and Development partners, 2. Policy maker and Decision Maker
17. FEASIBILITY STUDY
Is a "Feasibility Study " for the Project requied?
18. SOCIAL & ENVIRONMENTAL IMPACT: (Briefly describe the effects of the project, if any, on the people and the surrounding environment. Will the project assist in alleviating poverty?)
1. No social and Environmental Impacts 2. This project will contribute to the sustainable livelihood enhancement referring to poverty reduction
19. CLIMATE CHANGE
a. Is any activity or output of the project related to Climate Change?
b. How is the project relevant to Climate Change?
Please select a Climate Change related sector of the project and fill up the contribution of the climate change related expenditure compared to the total project cost.
Climate Change-Related Sector
Percentage
Climate Change Relevance
20. DISASTER RISK REDUCTION
Is any activity or output of the project related to Disaster Risk Reduction?
21. GENDER ANALYSIS: (How does the project affect the roles of the men and women in the project area? Will women be actively involved in the implementation of the project?)
1. This project would not affect to the role of men and women in the project's location 2. Women will be actively involved in the project implementation
22. CAPACITY TO IMPLEMENT: (Does the Ministry have the skills and experience required to implement the project?)
Implement following the roles and responsibilities in the regulation and specific implement following the Mission of Tonle Sap Authority fulfill within the skills and experience for implement this projects.
23. STATUS OF PROJECT IMPLEMENTATION: (Provide a brief update on the progress of the project to date. Discuss any major problems causing delays in project implementation.)
24. PROJECT PRIORITY : (Please indicates the priority ranking of the project decided by the ministry/agency.)
1
25. DONOR INVOLVEMENT: (Provide any information on current or potential donor involvement in the project.)
Seeking the assistance
26. REFERENCE: (Please upload the project documents, MOU, or agreements with funding agencies including MEF.)

Part B: Project Costs and Funding Sources

( In US$’000 )
INVESTMENT COST20212022202320242025Total in 2023 - 2025Recurrent Cost Est.
Operational Expenditure
Salaries
Materials + Admin
Other
Capital Expenditure
Construction
Consultancy (i.e. TA)
Equipment + Furniture
Training
Other
TOTAL COST
FUNDING SOURCES20212022202320242025Total in 2023 - 2025Recurrent Cost Est.
Project Revenue
Government Funding
Cash Input
Other Resources
Donor Funding
TOTAL COMMITTED FUNDING
FUNDING REQUIRED

​Project Progress

27.
Quarter Expenditure Percentage of Achievement Progress Description User
Quarter 1 0 0
Quarter 2 0 0
Quarter 3 0 0
Quarter 4 0 0
Total 0 0